Events |
Event | Date | Status | Comment |
Application Received | 03/29/24 | | |
Completeness Review Completed | 04/25/24 | Incomplete | |
Applicant Notified Re: Completed CR | 04/25/24 | | |
Supplemental Material Submitted | 05/10/24 | | |
Application Deemed Complete | 05/28/24 | | |
Send Referrals | 05/29/24 | | |
Mail Public Notice | 06/10/24 | | signs posted 06/12/2024; reposted yellow, laminated signs on 06/28/2024 |
Public Hearing | 07/10/24 | Held & Closed | Applicant grants 43-day time extension 7/11 through 8/21. |
Record Closed | 08/21/24 | | |
Decision | 09/05/24 | Denied | |
Notice of Decision Sent | 09/06/24 | | Mailed copy of decision to applicant, owner and representatives 9/06/2024 |
Appeal Filed | 09/17/24 | | Approved timeline extension of 90-days to 120-day clock, which will postpone the Public Hearing date. New Public Hearing Date to occur before 01/30/2025 (Public Hearing date was required by 11/01/2024 prior to extension). |
Appeal Period Ends | 09/18/24 | | |
Decision Becomes Effective | 09/19/24 | | Appeal filed 9/17/2024 |
Mail Public Notice | 01/03/25 | | Appeal Hearing Public Notice |
Appeal Public Hearing | 01/14/25 | Held & Closed | Approved timeline extension of 90-days to 120-day clock, which will postpone the Public Hearing date. New Public Hearing Date to occur before 01/30/2025 (Public Hearing date was required by 11/01/2024 prior to extension). |
Appeal Public Hearing Deliberation | 01/28/25 | Scheduled | |