Events |
Event | Date | Status | Comment |
Application Received | 03/19/25 | | |
Completeness Review Completed | 04/09/25 | Incomplete | |
Applicant Notified Re: Completed CR | 04/09/25 | | |
Supplemental Material Submitted | 04/15/25 | | |
Completeness Review Completed | 04/30/25 | Incomplete | |
Supplemental Material Submitted | 05/22/25 | | |
Applicant Notified Re: Completed CR | 06/13/25 | | Notified of one more incomplete item on 6/13/25 |
Application Deemed Complete | 08/06/25 | | Applicant opted into HB2138 which does not require a public notice |
Send Referrals | 08/06/25 | | |
Decision | 10/03/25 | App with Conditions | Decision due within 63-days of being deemed complete |
Notice of Decision Sent | 10/06/25 | | Notice of Decision mailed to applicant/owner and their representative (HB2138) |