Events |
Event | Date | Status | Comment |
Application Received | 10/31/25 | | Timeline extension requested for 45 days from December 18, 2025 to March 4, 2026. |
Completeness Review Completed | 12/01/25 | Incomplete | |
Applicant Notified Re: Completed CR | 12/01/25 | | emailed applicant with details of incomplete application- MHD |
Supplemental Material Submitted | 12/03/25 | | |
Supplemental Material Submitted | 12/11/25 | | |
Application Deemed Complete | 12/18/25 | | 12/18/25 Sent email to applicant notifying them that this application has been deemed complete. -MHD |
Mail Public Notice | 12/26/25 | | |
Application Deemed Complete | 01/30/26 | | Deemed complete a second time after additional materials were submitted |
Mail Public Notice | 02/03/26 | | mailed second initial public notice for new comment period after application was deemd complete again on 01/30/2026 |
Decision | 03/09/26 | Approved | Eugene Code EC 9.6210(2)(a)(2). L-2 Low Screen Landscape standards, EC 9.6735(2) Public Access standards |
Decision | 03/09/26 | Denied | EC 9.6792(3)(b)(2) Stormwater Quality standards |