| 120 Wall/Vault Insulation | Reviewed | 07/21/23 | SEGalbreath | 416 wall insulation and RC OK except at balcony |
| 120 Wall/Vault Insulation | Cancelled | 07/24/23 | SEGalbreath | No inspections for this today |
| 120 Wall/Vault Insulation | Reviewed | 07/27/23 | SEGalbreath | Walls OK in 315,16,19,22, 234 |
| 120 Wall/Vault Insulation | Reviewed | 07/28/23 | SEGalbreath | Ceiling insulation OK at following units. Pictures OK of progress for RC. 417,18,21,22. (22 has some ducting and insulation needed in corner where mechanical vents terminate at exterior wall). RC and wall insulation Ok in 232 and 234 except for balcony. |
| 120 Wall/Vault Insulation | Cancelled | 08/01/23 | SEGalbreath | Nothing inspected today |
| 120 Wall/Vault Insulation | Reviewed | 08/03/23 | SEGalbreath | 515,516,530 OK. 531 needs wall insulation above ceiling line at seismic joint. 430,440,441 OK for wall top out. 417,418,419,420,421,422 OK to finish sheet rock. 330,331 OK for walls. 230 OK for walls. **Previous rough mechanical and framing inspections done for these units except at balconies** |
| 120 Wall/Vault Insulation | Reviewed | 08/04/23 | SEGalbreath | . RC and wall insulation OK 229 except balcony and furred wall by corridor/seismic joint. 315,316,339 OK. 437,438 ceiling insulation/RC ok. 416,430,432 OK to insulate ceiling once FSA's finished. |
| 120 Wall/Vault Insulation | Reviewed | 08/07/23 | SEGalbreath | 214-220 wall insulation OK. 232,234 wall insulation and RC OK. 229 needs furred walls insulated. 339 wall insulation and RC OK. 330 needs furred walls insulated. 417-411 ceiling insulation and RC OK. 431,32,40,60 Fire caulking above ceiling line OK. 515,516,530 need furred walls insulated. |
| 120 Wall/Vault Insulation | Reviewed | 08/09/23 | SEGalbreath | Wall insulation and RC: 214-221 (Need to check FSA's at tub dead spaces, and balcony fixes still pending) |
| 120 Wall/Vault Insulation | Cancelled | 08/11/23 | SEGalbreath | No insulation looked at today |
| 120 Wall/Vault Insulation | Reviewed | 08/15/23 | SEGalbreath | Ceiling insulation and RC 431,440. Wall insulation and RC 415 (except at balcony). |
| 120 Wall/Vault Insulation | Cancelled | 08/17/23 | SEGalbreath | Per text from Kevin |
| 120 Wall/Vault Insulation | Reviewed | 08/18/23 | SEGalbreath | 229 walls and RC OK |
| 120 Wall/Vault Insulation | Reviewed | 08/21/23 | SEGalbreath | Ceiling insulation and RC: 44 needs wall fix finished, 432 OK, 430 needs furred wall insulated, 416 insulation OK, pics OK for RC. |
| 120 Wall/Vault Insulation | Reviewed | 08/22/23 | SEGalbreath | Ceiling insulation RC ok in 416. Wall insulation and RC ok in 235,236,237,238 except at 238 demising wall |
| 120 Wall/Vault Insulation | Reviewed | 08/23/23 | SEGalbreath | Wall insulation and RC at 231,233 |
| 120 Wall/Vault Insulation | Reviewed | 08/28/23 | SEGalbreath | Ceiling insulation/RC 317,318; Above ceiling insulation/RC 214,215,216; Wall insulation/RC 239 |
| 120 Wall/Vault Insulation | Cancelled | 08/30/23 | SEGalbreath | None inspected today |
| 120 Wall/Vault Insulation | Cancelled | 08/31/23 | SEGalbreath | No insulation inspected today |
| 120 Wall/Vault Insulation | Reviewed | 09/01/23 | SEGalbreath | Ceiling insulation and RC 315-322 |
| 120 Wall/Vault Insulation | Reviewed | 09/06/23 | SEGalbreath | Ceiling insulation and RC 338,339 |
| 120 Wall/Vault Insulation | Cancelled | 09/08/23 | SEGalbreath | No insulation inspected today |
| 120 Wall/Vault Insulation | Reviewed | 09/11/23 | SEGalbreath | ceiling insulation and RC 334-337 |
| 120 Wall/Vault Insulation | Cancelled | 09/12/23 | SEGalbreath | No insulation today |
| 120 Wall/Vault Insulation | Cancelled | 09/13/23 | SEGalbreath | No insulation inspected |
| 120 Wall/Vault Insulation | Cancelled | 09/14/23 | SEGalbreath | No insulation inspected today |
| 120 Wall/Vault Insulation | Cancelled | 09/15/23 | RZSteiner | |
| 120 Wall/Vault Insulation | Reviewed | 09/18/23 | RZSteiner | Ceiling insulation and RC channel in units 330,331,332,333,340,341 |
| 120 Wall/Vault Insulation | Reviewed | 09/22/23 | RZSteiner | RC channel and insulation in units 214-217,219-221,229,230 |
| 120 Wall/Vault Insulation | Reviewed | 10/02/23 | SEGalbreath | Units 234,238,239,240 Ceiling insulation and RC |
| 120 Wall/Vault Insulation | Reviewed | 10/06/23 | SEGalbreath | Level 1 wall insulation and RC: 112,13,14,16,17,18,19,27,28,29,30,21,32,33,34,36,37,38,39. |
| 120 Wall/Vault Insulation | Reviewed | 10/18/23 | SEGalbreath | Wall insulation: Seismic walls @ 309, 310, 313, 314, 326, 329. |
| 120 Wall/Vault Insulation | Reviewed | 10/20/23 | SEGalbreath | Level 7 tub pre-rock locations: 701-711, except 703 not ready; wall insulation 101-104 |
| 120 Wall/Vault Insulation | Reviewed | 10/23/23 | SEGalbreath | Ceiling RC and insulation 127,28,29. Tub pre-rock 703, 711-720. 127 needs blocking at interior wall. |
| 120 Wall/Vault Insulation | Reviewed | 10/24/23 | SEGalbreath | Ceiling insulation/RC 130-134 |
| 120 Wall/Vault Insulation | Reviewed | 10/25/23 | SEGalbreath | Tub pre rock insulation 301,302,303,304,305,307,309 |
| 120 Wall/Vault Insulation | Reviewed | 10/26/23 | SEGalbreath | Ext walls for high pre-rock: 105,6,7,8,9,20,22,24,25,26. (109 and 110 maybe needed at seismic? Checking with plans examiner). Ceiling insulation and RC 136,38,39. Pre rock areas for tubs/shear walls 301(tub only), 303,04,0 (when dry),07,08,09,10,11,13,12,14 |
| 120 Wall/Vault Insulation | Reviewed | 10/27/23 | SEGalbreath | Tub/shear pre rock insulation 323,24,25,26,27,28,29. Ceiling insulation and RC 112,113,114. |
| 120 Wall/Vault Insulation | Reviewed | 10/30/23 | FKamroyev | Unit insulation and RC channels at units 115-119 Partial perimeter steel stud framing at level 2 units 201-206 and 209 |
| 120 Wall/Vault Insulation | Reviewed | 11/01/23 | SEGalbreath | Level 4 Tub/Shear Wall/ Seismic wall insulation for pre-rock: 401 tubs only, 402 tubs/seismic; 03,04,05,07,08,12 tubs only; 410 tub/3hr wall; 11,14,23,24,25,27,28,29,OK; 442 tub only. |
| 120 Wall/Vault Insulation | Cancelled | 11/02/23 | SEGalbreath | Per contractor |
| 120 Wall/Vault Insulation | Reviewed | 11/03/23 | SEGalbreath | Level 6 tub pre-rock locations OK |
| 120 Wall/Vault Insulation | Reviewed | 11/06/23 | SEGalbreath | Ceiling insulation and RC 135/137. (137 ceiling on East end not ready) |
| 120 Wall/Vault Insulation | Reviewed | 11/07/23 | SEGalbreath | Insulation and RC 182 |
| 120 Wall/Vault Insulation | Reviewed | 11/08/23 | SEGalbreath | 202-205 OK for high pre-rock (walls done also) |
| 120 Wall/Vault Insulation | Reviewed | 11/09/23 | SEGalbreath | 710,711 interior shear walls. Upper wall areas at L7 electrical rooms |
| 120 Wall/Vault Insulation | Reviewed | 11/13/23 | SEGalbreath | Wall insulation for high pre-rock 201-210 ok except furred walls that need thermal insulation per plan. |
| 120 Wall/Vault Insulation | Reviewed | 11/14/23 | SEGalbreath | 2 sided shear walls 701/703 |
| 120 Wall/Vault Insulation | Reviewed | 11/16/23 | SEGalbreath | Framing/rough mechanical OK 710. Interior shear OK 701/703. Level 2 units framing/rough mechanical/insulation OK except dropped ceiling framing remains in 211-228. |
| 120 Wall/Vault Insulation | Reviewed | 11/17/23 | SEGalbreath | 703/705 insulation OK but need feeders done and fire caulked and putty pads on laundry valve boxes at rated walls. |
| 120 Wall/Vault Insulation | Cancelled | 11/20/23 | SEGalbreath | No insulation inspected today |
| 120 Wall/Vault Insulation | Cancelled | 11/22/23 | SEGalbreath | None inspected today |
| 120 Wall/Vault Insulation | Reviewed | 11/27/23 | SEGalbreath | Soffits/drops 135,37,39,184,132 |
| 120 Wall/Vault Insulation | Reviewed | 11/28/23 | SEGalbreath | Level 5 tub/seismic walls pre rock only: 501-513 tubs only except 502 tub/seismic. 542 tub/seismic |
| 120 Wall/Vault Insulation | Reviewed | 12/04/23 | SEGalbreath | Level 5 insulation: Pre-rock at tubs and at walls with interior shear. Mineral wool fireblocking at demising walls. (no insulation in demising walls without interior shear yet) 509,510,511,523-528. |
| 120 Wall/Vault Insulation | Reviewed | 12/05/23 | SEGalbreath | level 7 units 701-706 wall insulation and RC: 701 insulation ok, no RC, 702 OK except seismic wall. Also needs 2layers of gyp above ceiling line at stairwell shaft. 703 no RC, needs gyp completed on South side of elevator shaft and above ceiling line, insulation OK. 704 insulation OK, RC partial. 705 & 706 OK. |
| 120 Wall/Vault Insulation | Reviewed | 12/07/23 | SEGalbreath | Level 7: 701-703 pre rock ok except small spot pointed out in 703. 705 OK to proceed with gyp. Wall insulation and RC 707,708 |
| 120 Wall/Vault Insulation | Reviewed | 12/08/23 | SEGalbreath | Level 7 units, wall insulation/RC. 703,709-713,715 |
| 120 Wall/Vault Insulation | Reviewed | 12/11/23 | SEGalbreath | Level 7 units wall/vault and RC: 714,717,719 ok. 716 and 718 need fire blocking at furred walls and shaft walls completed behind furred walls. |
| 120 Wall/Vault Insulation | Reviewed | 12/12/23 | SEGalbreath | Level 6 insulation/RC: 601 insulation at shear wall only, 602 has some fire caulking needed, 603 shear wall insulation OK, needs fire blocking at furred wall, 601,611 insulation at shear walls OK. Level 7: 719,720,721 insulation/RC OK. |
| 120 Wall/Vault Insulation | Reviewed | 12/13/23 | SEGalbreath | 601,602,603 bearing walls OK, 716,718 OK. |
| 120 Wall/Vault Insulation | Reviewed | 12/15/23 | SEGalbreath | 180,181A,186 |
| 120 Wall/Vault Insulation | Reviewed | 12/19/23 | SEGalbreath | 601-608 wall insulation OK minus seismic walls in 602/607, and furred walls where insulation needed for fire blocking. |
| 120 Wall/Vault Insulation | Reviewed | 12/20/23 | SEGalbreath | 753,54,55,56 |
| 120 Wall/Vault Insulation | Reviewed | 12/21/23 | AEParrish | Looked at wall insulation on level 6, rooms 610 and 612. Also level 7, rooms 751 and 752. |
| 120 Wall/Vault Insulation | Reviewed | 12/22/23 | AEParrish | Lid insulation in rooms 182, 183 &184. Wall insulation in rooms 611,613, 614, 616, 617, 653, 654 & 655.
|
| 120 Wall/Vault Insulation | Reviewed | 12/28/23 | RZSteiner | RC channel and insulation units 610-620 |
| 120 Wall/Vault Insulation | Reviewed | 12/29/23 | RZSteiner | Party/corridor walls in units 402 and 442 |
| 120 Wall/Vault Insulation | Reviewed | 01/03/24 | SEGalbreath | RC/wall insulation 621 |
| 120 Wall/Vault Insulation | Reviewed | 01/05/24 | SEGalbreath | Seismic walls 342/302, 178 |
| 120 Wall/Vault Insulation | Reviewed | 01/08/24 | SEGalbreath | Level 5 units: Wall insulation only (no RC) 542,501-507. 506 needs seismic wall. |
| 120 Wall/Vault Insulation | Reviewed | 01/09/24 | SEGalbreath | Wall insulation no RC 508,509,510. |
| 120 Wall/Vault Insulation | Reviewed | 01/10/24 | SEGalbreath | Wall insulation 551.553,554,555,556 |
| 120 Wall/Vault Insulation | Reviewed | 01/11/24 | SEGalbreath | wall insulation Electrical rooms 551,53,55. 453,4,5. 354 A,B. |
| 120 Wall/Vault Insulation | Reviewed | 01/12/24 | SEGalbreath | Ceiling insulation level 6 units: 601-607 |
| 120 Wall/Vault Insulation | Reviewed | 01/18/24 | SEGalbreath | Level 5 units, Wall insulation/RC: 542, 501-514, 523. (542, needs work at dead space for rating continuity, 501 and 506 seismic wall remains.) |
| 120 Wall/Vault Insulation | Reviewed | 01/19/24 | SEGalbreath | Level 6 electric/equipment rooms: 651, 652, 653, 654A, 655, 656, 657. |
| 120 Wall/Vault Insulation | Reviewed | 01/22/24 | SEGalbreath | Level 6 units ceiling insulation/RC: 608-613. Level 5 units wall insulation/RC: 524-529 |
| 120 Wall/Vault Insulation | Reviewed | 01/23/24 | SEGalbreath | Ceiling insulation/RC 614, 616. |
| 120 Wall/Vault Insulation | Reviewed | 01/24/24 | SEGalbreath | Level 6 units Ceiling insulation/RC: 615,617-621 |
| 120 Wall/Vault Insulation | Reviewed | 01/29/24 | AEParrish | Contractor said that inspection was completed on 1/26/2024 by S. G. |
| 120 Wall/Vault Insulation | Reviewed | 01/31/24 | SEGalbreath | 562 OK, Dead space at 542 needs insulation and ceiling membrane per floor ceiling assembly on plans. |
| 120 Wall/Vault Insulation | Reviewed | 02/01/24 | SEGalbreath | Wall insulation 451 |
| 120 Wall/Vault Insulation | Reviewed | 02/05/24 | RZSteiner | Insulation and RC channel units 401-410, 442, 451 |
| 120 Wall/Vault Insulation | Reviewed | 02/06/24 | FKamroyev | North elevator 1&2 insulation at levels 4-7 |
| 120 Wall/Vault Insulation | Reviewed | 02/07/24 | SEGalbreath | Elevator1/2 Level 3 and Level 4. |
| 120 Wall/Vault Insulation | Reviewed | 02/08/24 | SEGalbreath | Level 4 units wall insulation/RC: 411-414, 423-429 |
| 120 Wall/Vault Insulation | Cancelled | 02/13/24 | SEGalbreath | No insulation inspected today |
| 120 Wall/Vault Insulation | Reviewed | 02/14/24 | SEGalbreath | Level 5 units, Ceiling RC and insulation: 542, 501-510 (542 has dead space remaining, 506 has seismic wall remaining). |
| 120 Wall/Vault Insulation | Reviewed | 02/15/24 | SEGalbreath | Level 6 ceiling insulation/RC: 658,653-657. 651 needs damper/access per previous conversations. Level3 wall insulation/RC: 349 OK except dead space, 302-310 OK except at seismic wall 306. |
| 120 Wall/Vault Insulation | Reviewed | 02/20/24 | SEGalbreath | Level 3 units wall insulation/RC (inspected 2/16): 311-329, 301*seismic. 544 dead space OK. Level 4 utility room insulation OK. 562 insulation ok. Level 5 units ceiling insulation/RC: 511,512, 523-529 |
| 120 Wall/Vault Insulation | Reviewed | 02/21/24 | SEGalbreath | 513/514 ceiling insulation/RC |
| 120 Wall/Vault Insulation | Reviewed | 02/22/24 | SEGalbreath | Level 4 units ceiling insulation/RC: 442, 401-408. Pump room exterior walls. |
| 120 Wall/Vault Insulation | Reviewed | 02/23/24 | SEGalbreath | 409,410 Ceiling insulation/RC |
| 120 Wall/Vault Insulation | Reviewed | 02/28/24 | SEGalbreath | Level 4 units ceiling insulation/RC: 411 needs insulation and ceiling membrane continuity at dead space against corridor wall, 412-414 OK, 423-425 OK. Also discussed that rating/firestop assembly at joints needed for whole turn down area at 5 story to 7 story on Levels 1 and 2. Some of these areas have been covered. |
| 120 Wall/Vault Insulation | Cancelled | 02/29/24 | SEGalbreath | Not ready per text from contractor |
| 120 Wall/Vault Insulation | Reviewed | 03/01/24 | SEGalbreath | 426-429 Ceiling insulation/RC, 251/252 wall insulation. |
| 120 Wall/Vault Insulation | Reviewed | 03/07/24 | SEGalbreath | Level 3 Ceiling insulation/RC: 342, 302-306 |
| 120 Wall/Vault Insulation | Reviewed | 03/08/24 | SEGalbreath | Level 3 units ceiling insulation/RC 307-309 |
| 120 Wall/Vault Insulation | Reviewed | 03/11/24 | SEGalbreath | Dead spaces at elevator 3/4 |
| 120 Wall/Vault Insulation | Cancelled | 03/13/24 | SEGalbreath | No insulation inspected today |
| 120 Wall/Vault Insulation | Reviewed | 03/14/24 | SEGalbreath | Level 3 units ceiling insulation/RC: 311-314,323,324. |
| 120 Wall/Vault Insulation | Reviewed | 03/15/24 | SEGalbreath | Level 3 units ceiling insulation/RC. 325-329. (328 and 329 not ready, 326 needs dead space ceiling gyp) |
| 120 Wall/Vault Insulation | Reviewed | 03/18/24 | RZSteiner | Units 328-329 with RC channel |
| 120 Wall/Vault Insulation | Reviewed | 03/20/24 | SEGalbreath | Stair 1, Stair 2 wall insulation: Need to verify if insulation required at ceiling stair 2. Stair 1 needs non FRT wood post removed. (not needed structurally) |
| 120 Wall/Vault Insulation | Reviewed | 03/26/24 | SEGalbreath | Metal stud wall between trash room and electrical room (170/171), Photos provided of ceiling at exterior bump-in by Stair 2 |
| 120 Wall/Vault Insulation | Reviewed | 03/28/24 | SEGalbreath | Walls at back of trash room |
| 120 Wall/Vault Insulation | Reviewed | 03/29/24 | SEGalbreath | L2, L3 East corridor walls |
| 120 Wall/Vault Insulation | Cancelled | 04/01/24 | AEParrish | Cancelled by contractor. |
| 120 Wall/Vault Insulation | Reviewed | 04/04/24 | SEGalbreath | Ceiling ins/RC 301, L3 mech/electrical room ceilings. |
| 120 Wall/Vault Insulation | Reviewed | 04/08/24 | SEGalbreath | Rigid at fire pump room area walls, ceiling insulation at back of house rooms L4 |
| 120 Wall/Vault Insulation | Cancelled | 04/09/24 | SEGalbreath | |
| 120 Wall/Vault Insulation | Reviewed | 04/11/24 | RZSteiner | Rock wool for 3-M assembly in CMU gap at demo wall. |
| 120 Wall/Vault Insulation | Reviewed | 04/16/24 | SEGalbreath | 4/15. Elevator fronts L1/L2 |
| 120 Wall/Vault Insulation | Reviewed | 04/17/24 | SEGalbreath | Fire pump room walls |
| 120 Wall/Vault Insulation | Needed | | | |
| 130 Lath or Dry Wall | Reviewed | 02/24/23 | RZSteiner | 1st layer behind tubs and some 2nd layer at 2Hr walls. Units 127-139 |
| 130 Lath or Dry Wall | Reviewed | 03/03/23 | RZSteiner | RC channel and gyp behind tubs and shafts. Units 115-119 Two of the units will require a F/S Eng. judgement for plumbing stacks |
| 130 Lath or Dry Wall | Reviewed | 03/14/23 | JAJohannesen | reviewed drywall at seismic joints where CMU walls will be built. |
| 130 Lath or Dry Wall | Reviewed | 03/17/23 | JAJohannesen | level 3 area B firewall reviewed line 10 @ A-A.8 1st layer both sides OK. |
| 130 Lath or Dry Wall | Reviewed | 03/21/23 | JAJohannesen | level 3 firewall in area B ok, 3 layers on each side OK, (at inner steel stud stud wall) |
| 130 Lath or Dry Wall | Reviewed | 03/22/23 | JAJohannesen | level 4 line 12 wall reviewed, gyp will be removed though. will re inspect this. |
| 130 Lath or Dry Wall | Denied | 03/30/23 | RZSteiner | |
| 130 Lath or Dry Wall | Reviewed | 03/31/23 | RZSteiner | drywall nail inspection for 2nd layer level 2 area A at the seismic joints and 3rd layer 3 hour firewall level 3 area B |
| 130 Lath or Dry Wall | Reviewed | 04/05/23 | SEGalbreath | Metal stud framing, Level 4, area B @ 3Hr wall (North end) |
| 130 Lath or Dry Wall | Reviewed | 04/07/23 | SEGalbreath | Met with DW contractor rep Sal on site for 3hr fire wall on level 4, region B. OK to proceed with first layer. Advised that a solution should be developed for getting fire caulking in at gaps between gyp and ceiling (also gyp and exterior walls) per details 3 & 5 on A0.45 as the space appears to be too small to fire caulk correctly. Also advised that if using a different assembly than is on the plans, the new assembly should be submitted as supplemental information per OSSC 107.4 |
| 130 Lath or Dry Wall | Reviewed | 04/18/23 | SEGalbreath | 3 Hr wall at level 4, area B: OK to proceed with gyp, please see notes from FIRESTOP ASSEMBLIES inspection for same area. |
| 130 Lath or Dry Wall | Reviewed | 04/21/23 | SEGalbreath | Level 2 units previously approved for pre-rock OK to mud. |
| 130 Lath or Dry Wall | Reviewed | 05/03/23 | SEGalbreath | OK to proceed on Level 5 area D corridor lids |
| 130 Lath or Dry Wall | Reviewed | 05/09/23 | SEGalbreath | Gyp fastening at level 5 corridor top out |
| 130 Lath or Dry Wall | Reviewed | 05/16/23 | SEGalbreath | Progress check at level 4 corridors (seismic to seismic). Most gyp is installed. OK to proceed and start taping. |
| 130 Lath or Dry Wall | Reviewed | 06/20/23 | SEGalbreath | 559 elec. room OK to mud |
| 130 Lath or Dry Wall | Reviewed | 06/22/23 | SEGalbreath | RC in 540 |
| 130 Lath or Dry Wall | Reviewed | 06/26/23 | SEGalbreath | Inspector left notes in vehicle. Will update at next inspection |
| 130 Lath or Dry Wall | Reviewed | 06/28/23 | SEGalbreath | OK to proceed at 537, 535, 534 |
| 130 Lath or Dry Wall | Reviewed | 06/29/23 | SEGalbreath | 535 OK |
| 130 Lath or Dry Wall | Reviewed | 07/03/23 | SEGalbreath | 541 OK to drywall. 540 OK except at seismic wall (shear nailing). 431,33,34,35,36 OK to hang walls (or RC where needed). Some insulation will need to be pulled back to gyp extends to underside of floor. |
| 130 Lath or Dry Wall | Reviewed | 07/07/23 | SEGalbreath | 520,22,33,34,37,38,39 OK. 517,18,19,21, &36 are OK except at areas where parapet repairs remain. OK to proceed on unaffected areas. |
| 130 Lath or Dry Wall | Cancelled | 07/12/23 | SEGalbreath | Per phone call with Cannon Jones. |
| 130 Lath or Dry Wall | Reviewed | 07/13/23 | SEGalbreath | OK to top out walls @ 416. OK to finish ceiling insulation and RC @ 433,34,35,36. Insulation OK @ 440. Insulation & RC ok @ 438 |
| 130 Lath or Dry Wall | Reviewed | 07/14/23 | SEGalbreath | 540,541 OK |
| 130 Lath or Dry Wall | Reviewed | 07/18/23 | SEGalbreath | Insulation and RC ok at walls in 419,420,422,439,440,441. Insulation and RC OK in 434,35,36 |
| 130 Lath or Dry Wall | Cancelled | 07/19/23 | SEGalbreath | Per text from Cannon Jones |
| 130 Lath or Dry Wall | Reviewed | 07/20/23 | SEGalbreath | Wall insulation and RC: 317,18,20,21,22,34,35,36,37 OK; 333 needs FSA and insulation at dryer vent bay, 338 needs insulation at exterior, 340 needs insulation at corridor. 432 OK. Ceiling insulation and RC: 433 OK. |
| 130 Lath or Dry Wall | Reviewed | 07/24/23 | SEGalbreath | 416 wall insulation and RC OK except at balcony Drops and gyp level 5: 517,18,19,20,21,22,34,36,37,38,39 OK except at balconies and where truss fixes and/or mech termination work is happening in ceilings. Gyp pre rock progress check level 2 in 7 story side. |
| 130 Lath or Dry Wall | Cancelled | 07/25/23 | SEGalbreath | Cancelled per contractor |
| 130 Lath or Dry Wall | Reviewed | 07/27/23 | SEGalbreath | Gyp above ceilings OK 417-422, RC OK walls only @ 234,315,316,319,322 **except at balcony locations** |
| 130 Lath or Dry Wall | Reviewed | 07/28/23 | SEGalbreath | Ceiling insulation OK at following units. Pictures OK of progress for RC. 417,18,21,22. (22 has some ducting and insulation needed in corner where mechanical vents terminate at exterior wall). RC and wall insulation Ok in 232 and 234 except for balcony. |
| 130 Lath or Dry Wall | Cancelled | 08/01/23 | SEGalbreath | Nothing inspected today |
| 130 Lath or Dry Wall | Reviewed | 08/03/23 | SEGalbreath | Insulation/RC inspections: 515,516,530 OK. 531 needs wall insulation above ceiling line at seismic joint. 430,440,441 OK for wall top out. 417,418,419,420,421,422 OK to finish sheet rock. 330,331 OK for walls. 230 OK for walls. |
| 130 Lath or Dry Wall | Reviewed | 08/04/23 | SEGalbreath | Densglass at NE corner bumpout OK for 1st layer. RC and wall insulation OK 229 except balcony and furred wall by corridor/seismic joint. 315,316,339 OK. 437,438 ceiling insulation/RC ok. 416,430,432 OK to insulate ceiling once FSA's finished. |
| 130 Lath or Dry Wall | Reviewed | 08/11/23 | SEGalbreath | Gyp and FSA's above ceiling line at 332 and 333 |
| 130 Lath or Dry Wall | Reviewed | 08/15/23 | SEGalbreath | Ceiling insulation and RC 431,440. Wall insulation and RC 415 (except at balcony). FSA's above ceiling 330,331,338 |
| 130 Lath or Dry Wall | Cancelled | 08/17/23 | SEGalbreath | Per text from Kevin |
| 130 Lath or Dry Wall | Reviewed | 08/18/23 | SEGalbreath | Exterior gyp on North side and West side levels 1 & 2 OK , 339 above ceiling needs some patching. |
| 130 Lath or Dry Wall | Reviewed | 08/22/23 | SEGalbreath | Ceiling insulation RC ok in 416. Wall insulation and RC ok in 235,236,237,238 except at 238 demising wall |
| 130 Lath or Dry Wall | Reviewed | 08/23/23 | SEGalbreath | |
| 130 Lath or Dry Wall | Reviewed | 08/24/23 | SEGalbreath | Gyp fastening OK 515,16,30,31 |
| 130 Lath or Dry Wall | Reviewed | 08/30/23 | SEGalbreath | Gyp and metal soffit framing: 515,516,530,531, 415-422, 430-441, 460 elec. room all OK except at balconies. |
| 130 Lath or Dry Wall | Reviewed | 08/31/23 | SEGalbreath | 2nd layer exterior gyp at East face of SE corner |
| 130 Lath or Dry Wall | Reviewed | 09/01/23 | SEGalbreath | Ceiling insulation and RC 315-322 |
| 130 Lath or Dry Wall | Reviewed | 09/05/23 | SEGalbreath | Densglass on South and East side at SE corner, Levels 1/2, and East wall at NE corner Levels 1/2 (106/107, 206/207)
|
| 130 Lath or Dry Wall | Reviewed | 09/06/23 | SEGalbreath | Ceiling insulation and RC 338,339 |
| 130 Lath or Dry Wall | Reviewed | 09/08/23 | SEGalbreath | Gyp and FSA's above ceiling 229-236. a few small corrections pointed out and being fixed at time of inspection |
| 130 Lath or Dry Wall | Reviewed | 09/11/23 | SEGalbreath | ceiling insulation and RC 334-337 |
| 130 Lath or Dry Wall | Cancelled | 09/15/23 | RZSteiner | |
| 130 Lath or Dry Wall | Reviewed | 09/26/23 | SEGalbreath | Ceiling insulation/RC. 218,231-237. 530 needs bath ceiling installed still and ceiling fixed where fan was changed. |
| 130 Lath or Dry Wall | Reviewed | 09/29/23 | SEGalbreath | Level 3 Units @ 5 story (seismic to seismic) OK with exception of some areas at balconies and PTACs. We can verify these when looking at ceiling drops. |
| 130 Lath or Dry Wall | Reviewed | 10/02/23 | SEGalbreath | Units 234,238,239,240 Ceiling insulation and RC |
| 130 Lath or Dry Wall | Reviewed | 10/06/23 | SEGalbreath | Level 1 wall insulation and RC: 112,13,14,16,17,18,19,27,28,29,30,21,32,33,34,36,37,38,39. |
| 130 Lath or Dry Wall | Cancelled | 10/16/23 | SEGalbreath | No lath/DW today. Other inspections done and resulted |
| 130 Lath or Dry Wall | Reviewed | 10/17/23 | SEGalbreath | Level 2 gyp OK at 5 story. |
| 130 Lath or Dry Wall | Denied | 10/25/23 | SEGalbreath | pre-rock at level 7 tub/shower areas |
| 130 Lath or Dry Wall | Reviewed | 11/06/23 | SEGalbreath | Ceiling insulation and RC 135/137. (137 ceiling on East end not ready) Level 1 units progress on gyp looks good. |
| 130 Lath or Dry Wall | Reviewed | 11/07/23 | SEGalbreath | Insulation and RC 182 |
| 130 Lath or Dry Wall | Reviewed | 12/05/23 | SEGalbreath | level 7 units 701-706 wall insulation and RC: 701 insulation ok, no RC, 702 OK except seismic wall. Also needs 2layers of gyp above ceiling line at stairwell shaft. 703 no RC, needs gyp completed on South side of elevator shaft and above ceiling line, insulation OK. 704 insulation OK, RC partial. 705 & 706 OK. |
| 130 Lath or Dry Wall | Denied | 12/06/23 | SEGalbreath | Level 1 at 5 story: Rooms 182,83,83 not ready. South end of East corridor needs fire caulking in exterior wall before proceeding. Several units (112,116,117,127,129,135 and possibly others) have signs of water intrusion at bottom of exterior walls. Steps need to be taken to mitigate water intrusion before proceeding. OSSC 2303.2.8 prohibits closing in walls with frt wood without meeting moisture content requirements. Manufacture specs for insulation and drywall will also prohibit installation of wet materials or closing in wet wall spaces. A representative amount of areas will need to have gyp removed and wood moisture tested. Any wet/damaged materials need to be removed and replaced as necessary. This applies to any similar areas/conditions in the building. |
| 130 Lath or Dry Wall | Reviewed | 12/07/23 | SEGalbreath | Level 7: 701-703 pre rock ok except small spot pointed out in 703. 705 OK to proceed with gyp. Wall insulation and RC 707,708 |
| 130 Lath or Dry Wall | Reviewed | 12/08/23 | SEGalbreath | Level 7 units, wall insulation/RC. 703,709-713,715 |
| 130 Lath or Dry Wall | Reviewed | 12/12/23 | SEGalbreath | Level 7 units progress: 701,704,707,708,711 OK to proceed. |
| 130 Lath or Dry Wall | Reviewed | 12/13/23 | SEGalbreath | 703,711,713 OK to gyp walls except at furred walls not yet fire blocked (elec rooms) |
| 130 Lath or Dry Wall | Reviewed | 12/15/23 | SEGalbreath | Level 1 units in 7 story |
| 130 Lath or Dry Wall | Reviewed | 12/18/23 | SEGalbreath | 714--719 Ceilings OK to proceed |
| 130 Lath or Dry Wall | Reviewed | 01/02/24 | SEGalbreath | Level 7 units |
| 130 Lath or Dry Wall | Reviewed | 01/03/24 | SEGalbreath | RC/wall insulation 621 |
| 130 Lath or Dry Wall | Reviewed | 01/11/24 | SEGalbreath | Above ceiling gyp and FSAs: 610,611 |
| 130 Lath or Dry Wall | Reviewed | 01/18/24 | SEGalbreath | Exterior Dens @ NE corner (Level1,2) |
| 130 Lath or Dry Wall | Reviewed | 01/19/24 | SEGalbreath | Level 6 units, FSAs and gyp above ceiling: 615 |
| 130 Lath or Dry Wall | Reviewed | 01/22/24 | SEGalbreath | Level 6 units ceiling insulation/RC: 608-613. Level 6 units FSA's and gyp above ceiling: 612-614 OK, 616 -619, (Electrical room walls need work). Level 5 units wall insulation/RC: 524-529 |
| 130 Lath or Dry Wall | Reviewed | 01/23/24 | SEGalbreath | Level 6 units, FSAs/gyp above ceilings: 620/621. Ceiling insulation/RC 614, 616. |
| 130 Lath or Dry Wall | Reviewed | 01/24/24 | SEGalbreath | Level 6 units Ceiling insulation/RC: 615,617-621 |
| 130 Lath or Dry Wall | Reviewed | 01/31/24 | SEGalbreath | Dead space at 542 needs insulation and ceiling membrane per floor ceiling assembly on plans. |
| 130 Lath or Dry Wall | Reviewed | 02/05/24 | RZSteiner | Units 201-209 |
| 130 Lath or Dry Wall | Reviewed | 02/06/24 | FKamroyev | Exterior Dens at NE ground floor loading dock |
| 130 Lath or Dry Wall | Reviewed | 02/08/24 | SEGalbreath | Level 4 units wall insulation/RC: 411-414, 423-429. Level 5 above ceiling pre-rock/fsas: 510-542 inspected, all units need penetrations re-checked and fire caulk where missing. |
| 130 Lath or Dry Wall | Reviewed | 02/09/24 | SEGalbreath | Level 5 units above ceiling gyp/FSAs: 501-510 (501 and 506 have seismic walls remaining, 507 has work taking place at wall between unit and trash chute). 542 OK except dead space needs insulation and gyp per floor/ceiling assembly. Level 6 back of unit walls at utility rooms reviewed. 651 needs to have duct work explained since it penetrates rated wall between unit and room. |
| 130 Lath or Dry Wall | Reviewed | 02/13/24 | SEGalbreath | Level 2 units gyp fastening: 211-229 OK |
| 130 Lath or Dry Wall | Reviewed | 02/14/24 | SEGalbreath | Level 5 units, Ceiling RC and insulation: 542, 501-510 (542 has dead space remaining, 506 has seismic wall remaining). /Level 5 units FSAs and gyp above ceiling: 511-514, 523-527 (13 and 26 each have one spot that needs fire caulking). |
| 130 Lath or Dry Wall | Reviewed | 02/15/24 | SEGalbreath | Level 6 ceiling insulation/RC: 658,653-657. 651 needs damper/access per previous conversations. Level3 wall insulation/RC: 349 OK except dead space, 302-310 OK except at seismic wall 306. Elevator 1/2 at 7 progress check OK. Gyp and FSAs above ceiling OK in 528/529. |
| 130 Lath or Dry Wall | Reviewed | 02/20/24 | SEGalbreath | Level 3 units wall insulation/RC (inspected 2/16): 311-329, 301*seismic. 544 dead space OK. Level 4 utility room insulation OK. 562 insulation ok. Level 5 units ceiling insulation/RC: 511,512, 523-529. Above ceiling gyp/FSAs: 410-410,441 406 needs seismic wall, 407 needs trash chute wall. (inspected 2/16). 411-414, 423,424, 551,556. |
| 130 Lath or Dry Wall | Reviewed | 02/22/24 | SEGalbreath | Level 4 units ceiling insulation/RC: 442, 401-408. FSAs/gyp above lids 425-427. |
| 130 Lath or Dry Wall | Reviewed | 02/23/24 | SEGalbreath | 409,410 Ceiling insulation/RC |
| 130 Lath or Dry Wall | Reviewed | 02/27/24 | SEGalbreath | L2 corridor ceilings OK except at seismic/CMU wall areas until firestopping installed at construction joints. 428/429 gyp/FSAs above ceiling OK. Pump room L1 gyp OK. |
| 130 Lath or Dry Wall | Reviewed | 02/28/24 | SEGalbreath | Level 4 units ceiling insulation/RC: 411 needs insulation and ceiling membrane continuity at dead space against corridor wall, 412-414 OK, 423-425 OK. Also discussed that rating/firestop assembly at joints needed for whole turn down area at 5 story to 7 story on Levels 1 and 2. Some of these areas have been covered. |
| 130 Lath or Dry Wall | Reviewed | 03/01/24 | SEGalbreath | Level 5 units fastening, 426-429 Ceiling insulation/RC, 411 dead space ceiling, progress check elevator dead space Level 3. |
| 130 Lath or Dry Wall | Reviewed | 03/04/24 | SEGalbreath | Level 3 gyp/FSAs above ceiling: 342 ok except dead space, 302-310 ok except seismic wall remains @ 306. 302 needs work at dead space by elevator. Head of wall OK @ elevator 3/4. |
| 130 Lath or Dry Wall | Reviewed | 03/07/24 | SEGalbreath | Level 3 Ceiling insulation/RC: 342, 302-306. North elevator dead spaces 3-7 |
| 130 Lath or Dry Wall | Reviewed | 03/08/24 | SEGalbreath | L6 corridor framing/rough mech/FSA's/gyp for cover: Not ready at garage seismic wall area, 3hr wall, or North elevator areas. Elevator room 165B framing OK, South Stair OK. |
| 130 Lath or Dry Wall | Reviewed | 03/11/24 | SEGalbreath | Level 4 units fastening 442,401-411. (401 and 406 have seismic wall remaining). Level 3 Above ceiling gyp/fsa's: 325-329 (328 needs truss ends protected where penetrating corridor wall). |
| 130 Lath or Dry Wall | Reviewed | 03/14/24 | SEGalbreath | Level 3 units ceiling insulation/RC: 311-314,323,324. Level 4 units gyp fastening: 411-429 |
| 130 Lath or Dry Wall | Reviewed | 03/15/24 | SEGalbreath | Level 5 Corridor framing/rough mechanical/gyp/FSAs from 508 West: Access needed for damper, hold gyp back by seismic joint and 3 hr wall until ready. Conduit not fire caulked at electrical room by elevator. |
| 130 Lath or Dry Wall | Reviewed | 03/18/24 | RZSteiner | Lid of dead space unit 326. |
| 130 Lath or Dry Wall | Reviewed | 03/26/24 | SEGalbreath | Level 3 units fastening: 342, 302-310 except seismic wall @ 306. Exterior densglass above door to trash room. |
| 130 Lath or Dry Wall | Reviewed | 03/28/24 | SEGalbreath | Stair 2 gyp does not continue through behind landings per detail on plans. A revised detail may be needed. Checking with Building Official. |
| 130 Lath or Dry Wall | Reviewed | 04/02/24 | SEGalbreath | 301 above ceiling gyp/FSA's. Gyp fastening Level 3 311-329 |
| 130 Lath or Dry Wall | Reviewed | 04/04/24 | SEGalbreath | L4 corridor to 408 except FSA's needed at 3hr wall and electrical room by elevator NW. Fire pump room OK to install rigid insulation on CMU/concrete walls. |
| 130 Lath or Dry Wall | Reviewed | 04/09/24 | SEGalbreath | 301 fastening |
| 130 Lath or Dry Wall | Needed | | | |
| 131 Firestop Assemblies | Reviewed | 04/18/23 | SEGalbreath | **Correction needed** Fire caulking at top of 3hr wall (Level 4, area B) needs to be kept dry, or provide documentation from manufacturer that material installed in wet location conforms to product installation instructions and listing criteria. OSSC 714.2. Caulking missing at top of wall at corridor. Please also coordinate application of caulking with installation of gypsum as there is not adequate space to properly caulk as constructed. |
| 131 Firestop Assemblies | Reviewed | 05/19/23 | SEGalbreath | OK to proceed at 3hr wall, level 5 North side |
| 131 Firestop Assemblies | Reviewed | 05/26/23 | SEGalbreath | Verified mono-coat spray on fire proofing of steel structural members level 1, aread D. Pending special inspections. |
| 131 Firestop Assemblies | Reviewed | 06/09/23 | SEGalbreath | OK to proceed at tub pre-rock locations 1st floor podium |
| 131 Firestop Assemblies | Reviewed | 06/20/23 | SEGalbreath | See framing. Units 432-434 OK at cover stage |
| 131 Firestop Assemblies | Reviewed | 06/21/23 | SEGalbreath | Verified caulking at A/B seismic level 3, and Level 1 CMU to PT deck fire caulking. |
| 131 Firestop Assemblies | Reviewed | 06/27/23 | SEGalbreath | Level 3 and level 4 electrical rooms (460/360). 338,33,335 OK. 334,336,337 need dryer ducting and nail plates needed. Can check at wall/vault. |
| 131 Firestop Assemblies | Info Only | 06/28/23 | SEGalbreath | Discussed inspection process for seismic joint |
| 131 Firestop Assemblies | Reviewed | 07/27/23 | SEGalbreath | Fire caulking at walls above ceiling line OK 417-422 |
| 131 Firestop Assemblies | Reviewed | 08/03/23 | SEGalbreath | Insulation/RC inspections: 515,516,530 OK. 531 needs wall insulation above ceiling line at seismic joint. 430,440,441 OK for wall top out. 417,418,419,420,421,422 OK to finish sheet rock. 330,331 OK for walls. 230 OK for walls. |
| 131 Firestop Assemblies | Reviewed | 08/07/23 | SEGalbreath | 214-220 wall insulation OK. 232,234 wall insulation and RC OK. 229 needs furred walls insulated. 339 wall insulation and RC OK. 330 needs furred walls insulated. 417-411 ceiling insulation and RC OK. 431,32,40,60 Fire caulking above ceiling line OK. 515,516,530 need furred walls insulated. |
| 131 Firestop Assemblies | Reviewed | 08/08/23 | SEGalbreath | Ok for ceiling insulation and RC: 317-322 and 360 (except at balconies) |
| 131 Firestop Assemblies | Reviewed | 08/09/23 | SEGalbreath | FSA's above ceiling line 315,16,34,35,36,37,40 (Except at balcony locations). 262A mech room. |
| 131 Firestop Assemblies | Reviewed | 08/10/23 | SEGalbreath | Pictures will be OK for some of the corrections from last few days |
| 131 Firestop Assemblies | Reviewed | 08/11/23 | SEGalbreath | Gyp and FSA's above ceiling line at 332, 333 |
| 131 Firestop Assemblies | Reviewed | 08/15/23 | SEGalbreath | Gyp and FSA's above ceiling line 330,331,338 |
| 131 Firestop Assemblies | Cancelled | 08/17/23 | SEGalbreath | Per text from Kevin |
| 131 Firestop Assemblies | Reviewed | 08/22/23 | SEGalbreath | Level 4 corridor and elec room above ceiling OK. 415, 340 FSA's above ceiling OK |
| 131 Firestop Assemblies | Reviewed | 08/23/23 | SEGalbreath | FSA's above ceiling 217,218,221 |
| 131 Firestop Assemblies | Reviewed | 08/24/23 | SEGalbreath | Level 3 corridor above hard lids seismic to seismic |
| 131 Firestop Assemblies | Reviewed | 08/28/23 | SEGalbreath | Ceiling insulation/RC 317,318; Above ceiling insulation/RC 214,215,216; Wall insulation/RC 239 |
| 131 Firestop Assemblies | Cancelled | 08/30/23 | SEGalbreath | None inspected today |
| 131 Firestop Assemblies | Reviewed | 08/31/23 | SEGalbreath | Line sets in dead spaces still need work at top |
| 131 Firestop Assemblies | Reviewed | 09/08/23 | SEGalbreath | Gyp and FSA's above ceiling 229-236. a few small corrections pointed out and being fixed at time of inspection |
| 131 Firestop Assemblies | Reviewed | 09/12/23 | SEGalbreath | 1) Above ceiling line fire caulking 237,238,239. 2) 23-04623-01 |
| 131 Firestop Assemblies | Reviewed | 09/14/23 | SEGalbreath | Soffits/drop lids and (rough mech) 415-411, 430-441 (430 has 1 missing bath fan) |
| 131 Firestop Assemblies | Reviewed | 09/15/23 | RZSteiner | Level 1 corridor 127-137 area D and 113-119 area D. |
| 131 Firestop Assemblies | Reviewed | 10/10/23 | SEGalbreath | Soffits and dropped ceilings Level 3 @ 5 story OK. Caulking at Level 2 corridor wall to floor verified
|
| 131 Firestop Assemblies | Cancelled | 10/16/23 | SEGalbreath | No FSA's today. Other inspections performed and resulted. |
| 131 Firestop Assemblies | Reviewed | 10/17/23 | SEGalbreath | 130,133,134 above ceiling FSA's |
| 131 Firestop Assemblies | Reviewed | 10/18/23 | SEGalbreath | Above ceiling FSA's 131,132,136,138 |
| 131 Firestop Assemblies | Cancelled | 10/19/23 | SEGalbreath | Per text from Cannon Jones |
| 131 Firestop Assemblies | Reviewed | 10/20/23 | SEGalbreath | FSA's above ceiling 127,28,29 |
| 131 Firestop Assemblies | Reviewed | 10/23/23 | SEGalbreath | Above ceiling FSA's 135,37,38,39. 118&119 missing some fire caulking and insulation in the way. 135 and 137 will need progress checks as work continues. |
| 131 Firestop Assemblies | Reviewed | 10/24/23 | SEGalbreath | FSA's above ceiling 112-119, progress @ 135,137 |
| 131 Firestop Assemblies | Reviewed | 10/25/23 | SEGalbreath | Fire caulking at tub pre-rock areas level 7 |
| 131 Firestop Assemblies | Reviewed | 11/22/23 | SEGalbreath | Level 1 drops and Level 7 units framing/rough mechanical: 127-131, 133-136, 138 drops OK. 701-703, 709,711,714,720,721 need dryer nail plates checked for 2" extend past framing, 702 dryer vent is distorted at top plates, 711 needs blocking per previous memo. All units still need feeders and fire caulking at feeders. |
| 131 Firestop Assemblies | Reviewed | 12/01/23 | SEGalbreath | Framing/rough mechanical: 165E/654A OK. 126 needs solution for plumbing pipes disrupting membrane at demising walls and bath fan/ducting connected. |
| 131 Firestop Assemblies | Cancelled | 12/08/23 | SEGalbreath | No FSA's inspected today |
| 131 Firestop Assemblies | Reviewed | 12/21/23 | AEParrish | Looked at fire caulking around edge of ceiling that was sheet rocked in rooms 702, 709, 712, 720, and 721. Looked at fire caulking above lid in rooms 118, 119, 182, 183, and 184. |
| 131 Firestop Assemblies | Reviewed | 01/09/24 | SEGalbreath | Above ceiling FSAs/gyp: 601,602(except seismic),603,604. |
| 131 Firestop Assemblies | Reviewed | 01/10/24 | SEGalbreath | Level 6 gyp/FSA's above ceiling: 605-609 (607 seismic wall not ready) |
| 131 Firestop Assemblies | Reviewed | 01/11/24 | SEGalbreath | Above ceiling gyp and FSAs: 610,611 |
| 131 Firestop Assemblies | Reviewed | 01/12/24 | SEGalbreath | FSA's/gyp above ceiling 612-614. OK to take pics of fire-tape and proceed. |
| 131 Firestop Assemblies | Reviewed | 01/19/24 | SEGalbreath | Level 6 units, FSAs and gyp above ceiling: 615 |
| 131 Firestop Assemblies | Reviewed | 01/22/24 | SEGalbreath | Level 6 units FSA's and gyp above ceiling: 612-614 OK, 616 -619, (Electrical room walls need work). |
| 131 Firestop Assemblies | Reviewed | 01/23/24 | SEGalbreath | Level 6 units, FSAs/gyp above ceilings: 620/621. |
| 131 Firestop Assemblies | Reviewed | 02/02/24 | SEGalbreath | Level 6 gyp nailing inspection: All walls backing up to electrical rooms, elevator shafts, stair wells, and trash chute need to be verified per previous visits. Ceiling framing was to be pulled back so gyp could be continuous per assemblies on plans. Seismic walls also remain. OK to mud/tape unaffected areas only. Some gyp may need to be removed to verify fixes. |
| 131 Firestop Assemblies | Reviewed | 02/08/24 | SEGalbreath | Level 5 above ceiling pre-rock/fsas: 510-542 inspected, all units need penetrations re-checked and fire caulk where missing. Trash chute needs work to maintain membrane continuity on unit side. |
| 131 Firestop Assemblies | Reviewed | 02/09/24 | SEGalbreath | Level 5 units above ceiling gyp/FSAs: 501-510 (501 and 506 have seismic walls remaining, 507 has work taking place at wall between unit and trash chute). 542 OK except dead space needs insulation and gyp per floor/ceiling assembly. Level 6 back of unit walls at utility rooms reviewed. 651 needs to have duct work explained since it penetrates rated wall between unit and room. |
| 131 Firestop Assemblies | Reviewed | 02/14/24 | SEGalbreath | Level 5 units FSAs and gyp above ceiling: 511-514, 523-527 (13 and 26 each have one spot that needs fire caulking). |
| 131 Firestop Assemblies | Reviewed | 02/15/24 | SEGalbreath | FSAs above ceiling OK in 528/529. |
| 131 Firestop Assemblies | Reviewed | 02/20/24 | SEGalbreath | Above ceiling gyp/FSAs: 410-410,441 406 needs seismic wall, 407 needs trash chute wall. (inspected 2/16). 411-414, 423,424, 551,556. |
| 131 Firestop Assemblies | Reviewed | 02/21/24 | SEGalbreath | Level 6 units soffits/drops: 601-621 (601 needs exposed ducting addressed) |
| 131 Firestop Assemblies | Reviewed | 02/22/24 | SEGalbreath | FSAs/gyp above lids 425-427. |
| 131 Firestop Assemblies | Reviewed | 02/26/24 | FKamroyev | Level 1 corridor NE to NW corner breezeway ok; pending electrical feeder conduits at NW breezeway ok to cover the rest once fire and electrical approvals |
| 131 Firestop Assemblies | Reviewed | 02/27/24 | SEGalbreath | L2 corridor ceilings OK except at seismic/CMU wall areas until firestopping installed at construction joints. 428/429 gyp/FSAs above ceiling OK. |
| 131 Firestop Assemblies | Reviewed | 03/04/24 | SEGalbreath | Level 3 gyp/FSAs above ceiling: 342 ok except dead space, 302-310 ok except seismic wall remains @ 306. 302 needs work at dead space by elevator. Head of wall OK @ elevator 3/4. |
| 131 Firestop Assemblies | Reviewed | 03/07/24 | SEGalbreath | Level 3 Above ceiling gyp/FSA's: 311-324. 312 needs work at back of wall area. |
| 131 Firestop Assemblies | Reviewed | 03/07/24 | SEGalbreath | Level 7 Corridor hard lid framing/FSA's/rough mech.707-729 |
| 131 Firestop Assemblies | Reviewed | 03/08/24 | SEGalbreath | L6 corridor framing/rough mech/FSA's/gyp for cover: Not ready at garage seismic wall area, 3hr wall, or North elevator areas. Elevator room 165B framing OK, South Stair OK. |
| 131 Firestop Assemblies | Reviewed | 03/11/24 | SEGalbreath | Level 3 Above ceiling gyp/fsa's: 325-329 (328 needs truss ends protected where penetrating corridor wall). |
| 131 Firestop Assemblies | Reviewed | 03/15/24 | SEGalbreath | Level 5 Corridor framing/rough mechanical/gyp/FSAs from 508 West: Access needed for damper, hold gyp back by seismic joint and 3 hr wall until ready. Conduit not fire caulked at electrical room by elevator. |
| 131 Firestop Assemblies | Denied | 03/18/24 | RZSteiner | Need to re visit units 326,328 and 329. NR OSSC 110.5 |
| 131 Firestop Assemblies | Reviewed | 03/19/24 | SEGalbreath | Please consult with architect for questions at breezeway ceiling. (6K assembly does not match as built condition where floor joists transition from open web to dimensional lumber). There has also been dropped ceiling framing built. Insulation/RC OK in 329. FSA corrections made in 326/328 |
| 131 Firestop Assemblies | Info Only | 03/26/24 | SEGalbreath | Please obtain and reference installation guide for steel frames at stairwell fire doors. There are areas where gyp does not fit in behind frame and this will need to be verified to be per approved installation guidelines. Please also note that there are DWV cleanouts in unit separation walls that will need some type of rated cover or other means to maintain required fire resistive ratings in these areas. Previously noted issues at construction joints between parking garage and corridor as well as at podium turn down remain unresolved. |
| 131 Firestop Assemblies | Reviewed | 04/02/24 | SEGalbreath | 301 above ceiling gyp/FSA's. |
| 131 Firestop Assemblies | Reviewed | 04/04/24 | SEGalbreath | L4 corridor to 408 except FSA's needed at 3hr wall and electrical room by elevator NW. Fire pump room OK to install rigid insulation on CMU/concrete walls. |
| 131 Firestop Assemblies | Info Only | 04/09/24 | SEGalbreath | Went over provided firestop assemblies for construction joint at garage and podium turn down. Contractor to go through building and have mineral wool insulation placed in gap per listed assembly (min. 50% compressed, leave min. 1/2" at outside edged for sealant.). Mineral wool will be spot checked one area at a time to verify this before applying any more sealant. |
| 131 Firestop Assemblies | Reviewed | 04/17/24 | SEGalbreath | L3 corridors ceilings and unit drops except at seisimic/3hr wall areas |
| 131 Firestop Assemblies | Needed | | | |
| 121 Ceiling Grid | Needed | | | |
| 124 Final Insulation | Cancelled | 06/14/23 | FKamroyev | Cannon called and cancelled inspection for today. I called Fred and let him know ~KDO |
| 124 Final Insulation | Cancelled | 06/20/23 | SEGalbreath | Resulted under wall/vault |
| 124 Final Insulation | Cancelled | 06/21/23 | SEGalbreath | Resulted under wall/vault |
| 124 Final Insulation | Reviewed | 06/26/23 | SEGalbreath | Parapet walls A and B partial |
| 124 Final Insulation | Cancelled | 06/29/23 | SEGalbreath | for wall/vault |
| 124 Final Insulation | Cancelled | 07/03/23 | SEGalbreath | This was for wall/vault |
| 124 Final Insulation | Cancelled | 07/06/23 | SEGalbreath | For wall/vault |
| 124 Final Insulation | Cancelled | 07/11/23 | SEGalbreath | Resulted under wall/vault |
| 124 Final Insulation | Cancelled | 07/12/23 | SEGalbreath | Per phone call with Cannon Jones. |
| 124 Final Insulation | Needed | | | |
| 146 Fire Sprinklers | Reviewed | 05/11/23 | ATBrushett | Looked at the standpipe on the south west side of the building in the hallway. Hydro on this section of standpipe is completed and it is OK to cover the vertical portion that will be in sheetrock. the 5th floor sprinkler system is done but there are no approved plans and the change to provide upright protection needs review before the inspection. |
| 146 Fire Sprinklers | Cancelled | 05/17/23 | ATBrushett | Plans have not been approved and revisions to the attic area have not been submitted and approved |
| 146 Fire Sprinklers | Reviewed | 05/23/23 | ATBrushett | Reviewed a portion of 5th floor sprinkler system. Plans on site with notes and area reviewed. |
| 146 Fire Sprinklers | Reviewed | 06/02/23 | ATBrushett | 4Th floor cover inspection and hydro has been complete. Will need insulation inspections before covering the above ceiling space. 5th floor OK to cover all items addressed. |
| 146 Fire Sprinklers | Reviewed | 06/08/23 | ATBrushett | 3rd floor ok to cover and hydro |
| 146 Fire Sprinklers | Reviewed | 06/14/23 | ATBrushett | 2nd floor hydro and cover inspection OK as marked on the plans |
| 146 Fire Sprinklers | Reviewed | 06/20/23 | GRGordon | Fire Sprinkler Open Cover Inspection/Insulation Verification. Permit number: 21-07253-01.
Insulation in place in wall side bays; 4 rooms-517, 518, 521 and 536.
Provide sprinklers in corner pockets. (Heads installed in pockets in above rooms on second inspection. GRG). |
| 146 Fire Sprinklers | Reviewed | 07/18/23 | ATBrushett | 4th floor insulation cover OK the above ceiling space is full of insulation. |
| 146 Fire Sprinklers | Reviewed | 07/26/23 | KAHaggas | 5 Story, Level 1 Rough Sprinkler inspection: piping, supports, bracing, locations ok, hydro test ok, ok to cover; see jobsite plans also. |
| 146 Fire Sprinklers | Reviewed | 08/09/23 | KAHaggas | 5th Floor, South: flex heads set in corridor; ok to cover. |
| 146 Fire Sprinklers | Reviewed | 08/16/23 | ATBrushett | 4th floor phase 1 sprinklers in the hallway OK to cover |
| 146 Fire Sprinklers | Reviewed | 08/25/23 | ATBrushett | 3rd floor hallway ok to cover |
| 146 Fire Sprinklers | Reviewed | 08/30/23 | ATBrushett | Second floor hallway of the west system OK to cover |
| 146 Fire Sprinklers | Reviewed | 09/01/23 | KAHaggas | 3rd Floor Insulation above ceiling ok. |
| 146 Fire Sprinklers | Reviewed | 09/13/23 | ATBrushett | Walked the 4th floor phase one are and verified the drops being installed in the soffits. Also looked at the while on the 1st floor same area and they are ok to cover |
| 146 Fire Sprinklers | Reviewed | 09/20/23 | KAHaggas | 2nd Floor: insulation above ceiling ok. |
| 146 Fire Sprinklers | Reviewed | 10/06/23 | KAHaggas | 3rd Floor: sprinkler drops verified at dropped ceilings in bathrooms/closets, ok to cover |
| 146 Fire Sprinklers | Reviewed | 10/25/23 | ATBrushett | 5 story building 1st floor insulation above ceiling OK to cover |
| 146 Fire Sprinklers | Reviewed | 10/27/23 | ATBrushett | 2nd floor soffit areas on the 5 floor building OK to cover |
| 146 Fire Sprinklers | Cancelled | 11/02/23 | ATBrushett | Should have been standpipe inspection |
| 146 Fire Sprinklers | Reviewed | 11/14/23 | KAHaggas | Rough sprinkler inspection at 1st floor north, 7th floor: piping, supports, bracing, locations ok, hydro ok, see plans for specific locations. ok to cover. |
| 146 Fire Sprinklers | Reviewed | 11/17/23 | KAHaggas | 1st Floor hard lids and soffits - ok to cover |
| 146 Fire Sprinklers | Reviewed | 12/08/23 | KAHaggas | Rough Sprinkler Inspection, Units 124, 125, 125 1st Flr and 6th Flr all: piping, supports, bracing, locations ok; hydro test ok. Ok to Cover |
| 146 Fire Sprinklers | Reviewed | 12/13/23 | ATBrushett | 2nd floor hydro and cover OK |
| 146 Fire Sprinklers | Reviewed | 01/05/24 | KAHaggas | 5th Floor Rough Sprinkler inspection: piping, supports, bracing, locations ok, hydro test ok, ok to cover |
| 146 Fire Sprinklers | Reviewed | 01/10/24 | ATBrushett | 4th floor hydro and Cover OK except that the system still needs the bracing on the main piping in the hall |
| 146 Fire Sprinklers | Reviewed | 01/11/24 | ATBrushett | 7th floor soffit areas ok to cover and the 6th floor up to the fire wall is ok to cover. Insulation has been provided for the ceiling space in lieu of sprinklers |
| 146 Fire Sprinklers | Reviewed | 01/25/24 | ATBrushett | 3rd floor cover and hydro ok, Ok to cover besides still needing bracing in the corridors for the main piping. Finished the insulation inspections for the 6th floor, 6th floor ok to cover |
| 146 Fire Sprinklers | Reviewed | 02/13/24 | KAHaggas | 5th Floor, east side: ceiling insulation ok, ok to cover. |
| 146 Fire Sprinklers | Reviewed | 02/16/24 | ATBrushett | Stair 2 standpipe hydro and the rest off the first floor 6 inch feed inspected. areas marked on the job site plans. OK to cover |
| 146 Fire Sprinklers | Reviewed | 02/20/24 | ATBrushett | Insulation on the 5th floor was spot checked for fill. All spot check areas are Ok |
| 146 Fire Sprinklers | Reviewed | 02/22/24 | ATBrushett | spot checked insulation on the 4th floor up to the fire wall |
| 146 Fire Sprinklers | Reviewed | 02/28/24 | KAHaggas | 4th Flr ceiling insulation installed, ok to cover |
| 146 Fire Sprinklers | Reviewed | 03/08/24 | ATBrushett | Insulation inspections for floor 3 up to the fire wall OK, |
| 146 Fire Sprinklers | Cancelled | 03/15/24 | ATBrushett | re schedule for Monday |
| 146 Fire Sprinklers | Cancelled | 03/18/24 | IVRUser | |
| 146 Fire Sprinklers | Reviewed | 03/18/24 | KAHaggas | 3rd Floor, Rooms 311-329: Insulation ok, ok to cover. |
| 146 Fire Sprinklers | Reviewed | 03/29/24 | ESPhillips-Meadow | 7th level amenities - piping and bracing in place. Hydro 2 hrs @ 220psi, ok. |
| 146 Fire Sprinklers | Needed | | | |
| 147 Alarm Systems | Needed | | | |
| 144 Emergency Generator | Needed | | | |
| 153 Water/Hydrant System | Cancelled | 01/27/23 | ESPhillips-Meadow | contractor canceled |
| 153 Water/Hydrant System | Reviewed | 01/31/23 | ATBrushett | FDC and fire line have been installed, will need to provide electronic monitoring for the OS&Y valves since they will be in an above ground box. Also need to install a ball drip for the FDC that is accessible. Flush flow and hydro still need to be completed. |
| 153 Water/Hydrant System | Reviewed | 04/06/23 | ATBrushett | Ball drip has been installed in the FDC line and there is access provided |
| 153 Water/Hydrant System | Reviewed | 07/21/23 | KAHaggas | hydrostatic test ok. |
| 153 Water/Hydrant System | Needed | | | |
| 154 Standpipe | Reviewed | 11/02/23 | ATBrushett | Standpipe hydro and cover for supply piping and one cabinet riser. Bracing is in place and pipe size and outlet location is good. Need to provide a gage at the top of the 7 storey. |
| 154 Standpipe | Needed | | | |
| 143 Fire Regulation | Needed | | | |
| 150 Landscaping | Needed | | | Landscaping to be installed per Sheet O5_L3.00 |
| 919 Bicycle Parking | Needed | | | |
| 157 Zoning | Needed | | | All parking spaces marked "Compact" and sidewalk from parking structure to street along S. side of driveway. |
| 160 Emerg Egress Light | Needed | | | |
| 930 SPI Fabricated Items | Needed | | | |
| 931 SPI Steel Construction | Needed | | | |
| 162 SPI Concrete Construction | Needed | | | |
| 172 SPI Masonry Construction | Needed | | | |
| 176 SPI Soils | Needed | | | |
| 174 SPI Sprayed Fireproofing | Needed | | | |
| 181 SPI Fire-resist. Penetations | Needed | | | Inspection added by SEG for joint assembly at CMU walls to structure (garage and turn-down areas) |
| 180 SPI Epoxy/Expan/Screw Anchors | Needed | | | |
| 940 SPI Seismic(Structural Steel) | Needed | | | |
| 941 SPI Seismic(Structural Wood) | Needed | | | |
| 944 SPI Seismic(Arch Components) | Needed | | | |
| 945 SPI Anchorage/Emergency Power | Needed | | | |
| 955 SPI Anchorage/Vibration Isoltn | Needed | | | |
| 956 SPI Sprinkler Clearance | Needed | | | |
| 178 SPI Additional Inspections | Needed | | | |
| 950 Structural Observation | Needed | | | |
| 951 SPI Final Letter | Needed | | | |
| 199 Final Building | Needed | | | |
Electrical | Active | 08/23/22 | 04/27/25 | | |
| Inspection | Result | | Inspected | Inspector | Comment | |
| 210 Undergrnd/Slab Elec | Reviewed | 08/24/22 | JKGoschie | Zone 1 and 2 deep conduits. |
| 210 Undergrnd/Slab Elec | Reviewed | 08/26/22 | JKGoschie | Zone 1 and 2. See highlighted plans on site. |
| 210 Undergrnd/Slab Elec | Reviewed | 09/12/22 | JKGoschie | Main electrical room area. |
| 210 Undergrnd/Slab Elec | Reviewed | 09/15/22 | JKGoschie | See plan's on site. |
| 210 Undergrnd/Slab Elec | Reviewed | 09/19/22 | SJLenker | Deep underground conduits running at grid lines 8 & 11 on D line crossing courtyard #2 okay. |
| 210 Undergrnd/Slab Elec | Reviewed | 09/27/22 | JKGoschie | See plans on site. |
| 210 Undergrnd/Slab Elec | Reviewed | 09/28/22 | JKGoschie | See plans on site. |
| 210 Undergrnd/Slab Elec | Reviewed | 09/30/22 | JKGoschie | See plans on site. |
| 210 Undergrnd/Slab Elec | Reviewed | 10/07/22 | JKGoschie | See plans on site. |
| 210 Undergrnd/Slab Elec | Reviewed | 10/25/22 | JKGoschie | See plans on site. |
| 210 Undergrnd/Slab Elec | Reviewed | 11/02/22 | JKGoschie | Level 2 PT deck. |
| 210 Undergrnd/Slab Elec | Reviewed | 11/17/22 | JKGoschie | Level; 2 zone 1. |
| 210 Undergrnd/Slab Elec | Reviewed | 11/29/22 | JKGoschie | Level 2 zone 2 PT deck. |
| 210 Undergrnd/Slab Elec | Reviewed | 12/08/22 | JKGoschie | 3 PT deck. |
| 210 Undergrnd/Slab Elec | Reviewed | 12/09/22 | JKGoschie | Zone 4. |
| 210 Undergrnd/Slab Elec | Reviewed | 12/29/22 | JKGoschie | Zo9ne 1 Level 3 PT deck. |
| 210 Undergrnd/Slab Elec | Reviewed | 01/05/23 | JKGoschie | Level 2 zone 3. |
| 210 Undergrnd/Slab Elec | Reviewed | 01/23/23 | JKGoschie | PT 4. |
| 210 Undergrnd/Slab Elec | Reviewed | 01/26/23 | JKGoschie | Zone 2 PT#, Zone 4 level 2 PT. |
| 210 Undergrnd/Slab Elec | Reviewed | 02/07/23 | JKGoschie | Level 3 zone 3. Contractor sent picture for this inspection. |
| 210 Undergrnd/Slab Elec | Reviewed | 02/27/23 | JKGoschie | PT deck 5 in garage. |
| 210 Undergrnd/Slab Elec | Reviewed | 03/27/23 | JKGoschie | PT 6. |
| 210 Undergrnd/Slab Elec | Reviewed | 05/02/23 | JKGoschie | Level 7 pt deck. |
| 210 Undergrnd/Slab Elec | Reviewed | 04/19/24 | BARichardson | speakers and lighting in courtyards. |
| 210 Undergrnd/Slab Elec | Needed | | | |
| 215 Electrical - Feeder | Reviewed | 08/03/23 | JKGoschie | Levels 2, 3, and 4 electrical rooms. |
| 215 Electrical - Feeder | Reviewed | 08/09/23 | JKGoschie | Level 5 zone C corridors. |
| 215 Electrical - Feeder | Reviewed | 08/11/23 | JKGoschie | Level 4 corridors. |
| 215 Electrical - Feeder | Reviewed | 08/23/23 | JKGoschie | Level 3 corridor |
| 215 Electrical - Feeder | Reviewed | 08/28/23 | JKGoschie | Level 2 corridors. |
| 215 Electrical - Feeder | Reviewed | 09/11/23 | JKGoschie | C 100 corridor. |
| 215 Electrical - Feeder | Reviewed | 03/20/24 | JKGoschie | MCC 1 and 2. |
| 215 Electrical - Feeder | Needed | | | |
| 217 Electrical Service | Cancelled | 03/20/24 | JKGoschie | |
| 217 Electrical Service | Reviewed | 03/21/24 | JKGoschie | EWEB at 1:54. MSA, SWB, SWC, Fire Pump. |
| 217 Electrical Service | Needed | | | |
| 213 Spec Bonding/Grounding | Reviewed | 11/04/22 | JKGoschie | 3 ground rods at service area. |
| 213 Spec Bonding/Grounding | Reviewed | 05/02/23 | JKGoschie | Pool 4 point bonding. |
| 213 Spec Bonding/Grounding | Cancelled | 03/20/24 | JKGoschie | |
| 213 Spec Bonding/Grounding | Reviewed | 03/21/24 | JKGoschie | Electrical room. |
| 213 Spec Bonding/Grounding | Needed | | | |
| 225 Elec Ceiling Cover | Cancelled | 07/26/23 | JKGoschie | |
| 225 Elec Ceiling Cover | Reviewed | 11/15/23 | JKGoschie | Units 101-107. |
| 225 Elec Ceiling Cover | Reviewed | 11/17/23 | JKGoschie | Level 1 soffits and ceilings. |
| 225 Elec Ceiling Cover | Reviewed | 04/03/24 | JKGoschie | Level 4 corridor |
| 225 Elec Ceiling Cover | Reviewed | 04/16/24 | JKGoschie | Level 3 corridor |
| 225 Elec Ceiling Cover | Needed | | | |
| 220 Rough Electrical | Reviewed | 02/03/23 | JKGoschie | Level 1 outside shear wall. |
| 220 Rough Electrical | Reviewed | 02/15/23 | BARichardson | Common wall between fire separation floors 1-5 for wall cover |
| 220 Rough Electrical | Cancelled | 03/09/23 | JKGoschie | |
| 220 Rough Electrical | Reviewed | 05/16/23 | JKGoschie | See spread sheet on site. |
| 220 Rough Electrical | Cancelled | 05/17/23 | JKGoschie | |
| 220 Rough Electrical | Reviewed | 06/02/23 | JKGoschie | Level 4 zones 5-7. |
| 220 Rough Electrical | Reviewed | 06/20/23 | JKGoschie | Level 3 zone D. |
| 220 Rough Electrical | Reviewed | 07/10/23 | JKGoschie | Level 2. |
| 220 Rough Electrical | Reviewed | 07/18/23 | JKGoschie | Units 533 and 538 ceilings. |
| 220 Rough Electrical | Cancelled | 07/25/23 | JKGoschie | |
| 220 Rough Electrical | Reviewed | 07/26/23 | JKGoschie | Level 1 zone D. |
| 220 Rough Electrical | Reviewed | 08/09/23 | JKGoschie | Level 5 zone C corridors. |
| 220 Rough Electrical | Reviewed | 08/11/23 | JKGoschie | Level 4 corridors. |
| 220 Rough Electrical | Reviewed | 08/23/23 | JKGoschie | Level 3 corridor. |
| 220 Rough Electrical | Reviewed | 08/28/23 | JKGoschie | |
| 220 Rough Electrical | Reviewed | 09/11/23 | JKGoschie | C 100 corridor, and shear wall between 5 story and 7 stoey. |
| 220 Rough Electrical | Reviewed | 09/13/23 | JKGoschie | Level 4 bathroom soffits and West side electrical room. |
| 220 Rough Electrical | Reviewed | 09/15/23 | JKGoschie | Level 1 of 7 story. |
| 220 Rough Electrical | Reviewed | 10/02/23 | JKGoschie | Unit 119 and shear walls 3-5. |
| 220 Rough Electrical | Reviewed | 10/09/23 | JKGoschie | Level 3 units soffits. |
| 220 Rough Electrical | Reviewed | 10/10/23 | JKGoschie | 7 story level 2 units. |
| 220 Rough Electrical | Reviewed | 10/26/23 | JKGoschie | Level 2 corridors |
| 220 Rough Electrical | Reviewed | 11/02/23 | JKGoschie | Units 302-310. |
| 220 Rough Electrical | Reviewed | 11/06/23 | JKGoschie | Units 301 and 342. |
| 220 Rough Electrical | Reviewed | 11/14/23 | JKGoschie | Level 7 units. |
| 220 Rough Electrical | Reviewed | 11/28/23 | JKGoschie | Ceilings 122-126, elevator mechanical rooms. |
| 220 Rough Electrical | Reviewed | 12/07/23 | JKGoschie | Ceilings in units 201-206. Rough in units 601-611. |
| 220 Rough Electrical | Reviewed | 12/08/23 | JKGoschie | Corridors, electrical , IDF, mechanical, storage rooms levels 3-7. |
| 220 Rough Electrical | Reviewed | 12/13/23 | JKGoschie | Level 2 ceiling in units 207-213, 222-228 |
| 220 Rough Electrical | Reviewed | 12/15/23 | JKGoschie | Units 612-621. |
| 220 Rough Electrical | Reviewed | 12/21/23 | JKGoschie | Wood framing in stairs 1 and 2. |
| 220 Rough Electrical | Reviewed | 12/29/23 | JKGoschie | Units 501-510, and 542. |
| 220 Rough Electrical | Reviewed | 01/10/24 | JKGoschie | Units 511-514, 523-529. |
| 220 Rough Electrical | Reviewed | 01/22/24 | JKGoschie | Units 401-410 and 442. |
| 220 Rough Electrical | Reviewed | 01/29/24 | JKGoschie | Units 411-414, 423-429. |
| 220 Rough Electrical | Reviewed | 02/06/24 | JKGoschie | Units 311-314, 323-329. |
| 220 Rough Electrical | Reviewed | 02/23/24 | JKGoschie | Levels 1 and 2 corridors and trash room walls. |
| 220 Rough Electrical | Reviewed | 03/01/24 | JKGoschie | Levels 6 and 7 corridors ceilings |
| 220 Rough Electrical | Reviewed | 03/15/24 | JKGoschie | Level 5 corridor ceiling. |
| 220 Rough Electrical | Reviewed | 04/03/24 | JKGoschie | Level 4 corridor. |
| 220 Rough Electrical | Reviewed | 04/16/24 | JKGoschie | Level 3 corridor. |
| 220 Rough Electrical | Needed | | | |
| 230 Limited Energy | Cancelled | 05/31/23 | JKGoschie | |
| 230 Limited Energy | Cancelled | 10/10/23 | JKGoschie | |
| 230 Limited Energy | Needed | | | |
| 299 Final Electrical | Cancelled | 04/29/24 | JKGoschie | |
| 299 Final Electrical | Reviewed | 04/30/24 | JKGoschie | 5 story level 3 East wing. |
| 299 Final Electrical | Reviewed | 04/30/24 | BARichardson | 5 story level 3 East wing. Units 331, 315, 332, 333, 334-340 |
| 299 Final Electrical | Reviewed | 05/02/24 | JKGoschie | |
| 299 Final Electrical | Needed | | | |
Fire | Active | 04/06/22 | 04/27/25 | | |
| Inspection | Result | | Inspected | Inspector | Comment | |
| 849 Final Fire | Needed | | | |
Mechanical | Active | 08/15/22 | 04/27/25 | | |
| Inspection | Result | | Inspected | Inspector | Comment | |
| 416 Rough Gas Piping | Reviewed | 12/21/23 | AEParrish | The gas line that was tested at 80 psi started in level 1 garage tees for level 1 corridor and goes to mechanical room 174, then goes to a gas riser that goes to level6 level 6 mechanical room 652 and corridor on level 6, then to level 6 garage. |
| 416 Rough Gas Piping | Needed | | | |
| 450 Final Gas Piping | Needed | | | |
| 420 Rough Mechanical | Reviewed | 04/26/23 | SEGalbreath | Reviewed 119. Looking into bath fan to see if damper is needed. Also need to verify how 100CFM fan is approved for kitchen area (code is 150 int.) |
| 420 Rough Mechanical | Info Only | 04/28/23 | SEGalbreath | Looked at few units with Tyler from Harvey and Price for condensate drains and radon piping. Advised that rough mechanical inspection will happen in units once ready for all mechanical and framing inspections. |
| 420 Rough Mechanical | Cancelled | 05/31/23 | SEGalbreath | Talked to Rob with Jet. Requested that inspections for rough mechanical happen at same time as framing and interior shear in units to minimize unnecessary site visits. |
| 420 Rough Mechanical | Reviewed | 06/02/23 | SEGalbreath | Units 535,537,538,540: Dryer vent nail plates need to extend min 2" from framing. OMSC 504.7. Inspector to check with building official about location of CRD at bath fans in lowered ceiling units. Also need to verify transfer air openings for cont. ventilation. |
| 420 Rough Mechanical | Reviewed | 06/05/23 | SEGalbreath | 533,534,536,539 OK. (dropped ceilings with bath fans to be verified later) |
| 420 Rough Mechanical | Cancelled | 06/06/23 | SEGalbreath | Per contractor. |
| 420 Rough Mechanical | Reviewed | 06/07/23 | SEGalbreath | 518,520,534,536 OK to insulate. Corrections for dryer vent nail plates to be verified before approving wall/vault in these units. |
| 420 Rough Mechanical | Reviewed | 06/08/23 | SEGalbreath | 517,519,521,522,532,541 OK except where ducting needs to be ran up through roof. |
| 420 Rough Mechanical | Cancelled | 06/09/23 | SEGalbreath | Per contractor |
| 420 Rough Mechanical | Reviewed | 06/13/23 | RZSteiner | Units 435,436,438 and 440. |
| 420 Rough Mechanical | Cancelled | 06/14/23 | FKamroyev | Cannon called and cancelled inspection for today. I called Fred and let him know ~KDO |
| 420 Rough Mechanical | Reviewed | 06/20/23 | SEGalbreath | 432-434 OK once dryer vent length labeled. |
| 420 Rough Mechanical | Reviewed | 06/21/23 | SEGalbreath | Follow up for level 5 units: 517 needs ducting completed and truss fix approved to cover, 518 OK for cover pending roof truss fix, 52i pending truss fix, 522 OK, 533 OK pending clarification on draft stop at demising wall, 534 OK, 535 OK pending truss fix, 536 OK, 537 OK, 538 OK pending truss fix. |
| 420 Rough Mechanical | Reviewed | 06/22/23 | SEGalbreath | 417,18,21 OK |
| 420 Rough Mechanical | Reviewed | 06/26/23 | SEGalbreath | Inspector left notes in vehicle. Will update at next inspection |
| 420 Rough Mechanical | Reviewed | 06/27/23 | SEGalbreath | Level 3 and level 4 electrical rooms (460/360). 338,33,335 OK. 334,336,337 need dryer ducting and nail plates needed. Can check at wall/vault. |
| 420 Rough Mechanical | Reviewed | 06/29/23 | SEGalbreath | 532, 317,318, 431 OK. 430 needs ducting finished. |
| 420 Rough Mechanical | Reviewed | 06/30/23 | SEGalbreath | 321 and 340 OK to insulate. Just need a couple of holes in top plate fire caulked, dryer vent nail plates, and ducting un-pinched in 321 |
| 420 Rough Mechanical | Reviewed | 07/03/23 | SEGalbreath | No new framing. Ok to insulate 315, 316, 319, 320, 321, 322, 333. Previous mechanical corrections for these can be seen at wall/vault inspection. |
| 420 Rough Mechanical | Reviewed | 07/06/23 | SEGalbreath | 430 corrections made |
| 420 Rough Mechanical | Reviewed | 07/07/23 | SEGalbreath | Mock ups for 533,535 OK. (Soffits and dropped ducting) |