City of Eugene
Planning & Development
Building and Permit Services
Permit Number: 25-05074-01
Date: 8/6/2026
Address: 890 W 5TH AVE
Project Description: 5-story Multi-Family - Whiteaker Commons
Application Type:
Commercial
Status:
Issued
Scope of Work:
New Apt Bldg (3+ units)
Zoning:
Community Commercial District
Map:
17-03-31-22
Tax Lot:
03501
Subdivision:
Packards Addition
Addition:
to Eugene
Lot:
4 & 5
Block:
Date Received:
07/31/25
# Bedrooms:
134
Commitment Date:
09/19/25
# Dwelling Units:
0
Ready to issue as of:
11/12/25
In Flood Plain:
Project Coordinator:
Kandra Hostetler
Phone:
541-682-5237
  
Sign Standards:
 
BUILDING CHARACTERISTICS
Construction Types:
3BS
Construction Type Comments:
 
OccupancyTypes:
R2
OSSC
Occupancy Type Comments:
B
 
Level 1 = 95; Levels 2-5 = 62 each thus 343 occs - ksh
S1
 
S2
Parking Garage (Open)
Occupancy Load:
343
Separated Building:
No
Fire Sprinklers:
Yes Required
NFPA13
Fire Alarms:
Yes Required
 
Building Area:
73889
Number of Stories:
5
Comment:
 
Floor Areas (sq ft):
Floor
Existing Floor Area
New Floor Area
Total Area
1st Floor
0
14993
14993
2nd Floor
0
14724
14724
3rd Floor
0
14724
14724
4th Floor
0
14724
14724
5th Floor
0
14724
14724
Existing floor area may not be shown.
CONTRACTOR DATA
Type
Contractor
Building
MEILI CONSTRUCTION
Electric
SUPERIOR ELECTRIC & CONSTRUCTION
Mechanical
COMFORT FLOW HEATING COMPANY LLC
Plumbing
TWIN RIVERS PLUMBING INC
Primary Contact
MAGEE MIKE
PLAN REVIEW SUMMARY
Plan review data displayed is the most current for each review. The applicant will receive notification of all issues needing additional information after all reviews on a project have been completed. Supplemental Information (SI) can be submitted prior to or after permit issuance. If you have any questions regarding your project, contact KSHostetler at 541-682-5237 or send email to kandra.s.hostetler@ci.eugene.or.us. Also note that some reviews (i.e., fire alarms, fire sprinklers) are deferred submittals and will be reviewed after original permit(s) have been issued.
Status Definitions
Pending
=
Review has not been started
Review
=
Under review
Waiting
=
Review for individual review has been completed, waiting for a response
External Wait
=
All reviews for project have been completed, waiting for a response
Approved
=
Review has been approved
Information
=
Information only, review not approved
Denied
=
Project cannot be approved as submitted
For information regarding the review of your project or the commitment date for completion of review, please contact your project coordinator, KSHostetler, at kandra.s.hostetler@ci.eugene.or.us or by phone at 541-682-5237.
Plan Review
Status
Review Completion Date
Project Coordination, Application Submittal
External Wait Time
09/18/25
Pre Issuance Coord, Pre Issuance SI
Approved
11/12/25
Post Issuance Coord, Post Issuance SI
Approved
07/21/26
Deferred Coordination, Deferred Submittal
Approved
07/02/26
Building, Application Submittal
Waiting for info
10/13/25
Building, Pre Issuance SI
Information
10/13/25
Building, Post Issuance SI
Approved
07/21/26
Building, Deferred Submittal
Waiting for info
06/08/26
Structural, Application Submittal
Waiting for info
09/11/25
Structural, Pre Issuance SI
Approved
11/07/25
Structural, Post Issuance SI
Approved
04/15/26
Structural, Deferred Submittal
Approved
07/01/26
Mechanical, Application Submittal
Waiting for info
09/11/25
Mechanical, Pre Issuance SI
Information
10/13/25
Electrical, Application Submittal
Approved
09/08/25
Electrical, Deferred Submittal
Approved
05/19/26
Plumbing, Application Submittal
Approved
08/20/25
Plumbing, Post Issuance SI
Approved
01/21/26
Zoning, Application Submittal
Waiting for info
09/05/25
Zoning, Pre Issuance SI
Approved
10/08/25
Zoning, Deferred Submittal
Approved
06/26/26
Public Works, Application Submittal
Waiting for info
09/17/25
Public Works, Pre Issuance SI
Approved
11/04/25
Public Works, Post Issuance SI
Information
02/03/26
Public Works, Deferred Submittal
Information
 
Stormwater Standards, Application Submittal
Waiting for info
09/17/25
Stormwater Standards, Pre Issuance SI
Approved
03/30/26
Stormwater Standards, Post Issuance SI
Approved
03/30/26
SDC, Application Submittal
Approved
09/17/25
SDC, Pre Issuance SI
Approved
11/21/25
SDC, Post Issuance SI
Information
02/03/26
Fire Marshal, Application Submittal
Waiting for info
09/18/25
Fire Marshal, Pre Issuance SI
Approved
10/09/25
Fire Marshal, Post Issuance SI
Approved
03/19/26
Fire Marshal, Deferred Submittal
Waiting for info
06/02/26
Erosion Inspection, Application Submittal
Approved
11/03/25
Emergency Generator, Deferred Submittal
Approved
07/02/26
Fire Alarm Plans, Deferred Submittal
Waiting for info
06/24/26
Fire Sprinkler Plans, Deferred Submittal
Approved
06/10/26
Water Main/Hydrant, Deferred Submittal
Approved
12/22/25
PERMITS AND INSPECTIONS
Permit Type
Status
 
Issued Date
Expiration Date
Completion Date
 
Building
Active
12/01/25
07/31/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
103 Footing
Cancelled
03/02/26
IVRUser
 
 
103 Footing
Reviewed
03/04/26
AEParrish
Rebar footing inspection for grid lines A-G and 1-14.1 ok pending SPI, this includes depend section that will be next to the utility vault in NE corner as shown on sheet S500 detail 6.
 
103 Footing
Reviewed
03/18/26
AEParrish
Rebar inspection for footings/grade beams for grid lines G-P.1 and 1-14.1 ok pending SPI, including depend section on S.E. corner of project.
 
103 Footing
Needed
   
 
105 Elec Rebar Ground
Reviewed
03/26/26
AEParrish
One grounding rebar tagged.
 
105 Elec Rebar Ground
Needed
   
 
108 Foundation
Reviewed
01/28/26
FKamroyev
Elevator walls appeared ok; need SPI report and pictures for elevator pad poured w/o city inspection. And need soils report prior to next inspection. Spoke w/ GC Scott.
 
108 Foundation
Reviewed
03/26/26
AEParrish
Rebar inspection for SOG (detail #9, sheet S500) from grid lines A-D, and 1-14 on North side of project ok pending SPI.
 
108 Foundation
Reviewed
04/02/26
AEParrish
Rebar inspection for SOG (detail #9, sheet S500) from grid lines D-O, and 1-14 on South side of project ok pending SPI.
 
108 Foundation
Needed
   
 
109 Foundation Drain/Waterproofing
Reviewed
04/02/26
AEParrish
4-inch perf pipe around perimeter of structure (grid lines A-D, and 1-14).
 
109 Foundation Drain/Waterproofing
Cancelled
04/21/26
IVRUser
 
 
109 Foundation Drain/Waterproofing
Reviewed
04/22/26
AEParrish
4 inch perf pipe around remainder of building grid lines D-O and 1-14.
 
109 Foundation Drain/Waterproofing
Needed
   
 
116 Underfloor Insulation
Reviewed
04/02/26
AEParrish
Bottom 16 inches of slab edge insulation on north half of project (grid lines A-D, and 1-14).
 
116 Underfloor Insulation
Cancelled
04/21/26
IVRUser
 
 
116 Underfloor Insulation
Reviewed
04/22/26
AEParrish
Bottom 16 inches of slab edge insulation on South half of project (grid lines D-O, and 1-14).
 
116 Underfloor Insulation
Needed
   
 
118 Framing
Needed
   
 
123 Floor Sheathing
Reviewed
04/22/26
AEParrish
Second floor sheathing nailing, grid lines A-D and 1-14.1, ok pending SPI.
 
123 Floor Sheathing
Cancelled
04/27/26
IVRUser
 
 
123 Floor Sheathing
Reviewed
04/28/26
AEParrish
Remainder of second floor - floor sheathing nailing, grid lines D-P and 1-14.1.
 
123 Floor Sheathing
Reviewed
05/08/26
AEParrish
Third floor sheathing grid lines A-d and1-14 ok pending SPI. (North section)
 
123 Floor Sheathing
Reviewed
05/13/26
AEParrish
Third floor sheathing grid lines D-O and 1-14 ok pending SPI.
 
123 Floor Sheathing
Reviewed
05/28/26
AEParrish
Level 4 floor sheathing from grid lines 1-14.1 and A-E, ok pending SPI.
 
123 Floor Sheathing
Reviewed
05/29/26
AEParrish
Inspected the rest of level 4 floor sheathing ok, pending SPI.
 
123 Floor Sheathing
Reviewed
06/10/26
AEParrish
Level 5 floor sheathing, grid lines A-D & 1-14.1 ok pending SPI.
 
123 Floor Sheathing
Reviewed
06/15/26
AEParrish
The rest of level 5 floor sheathing nailing and strapping ok, pending SPI.
 
123 Floor Sheathing
Needed
   
 
117 Roof Sheathing
Reviewed
07/09/26
AEParrish
Roof sheathing nailing and strapping, as well as parapet cover ok pending SPI.
 
117 Roof Sheathing
Needed
   
 
119 Exterior Shearwall
Reviewed
04/02/26
AEParrish
Above ground shear wall at SW corner of project (grid lines P-1) with embed plates, sheet S511 detail #5 ok pending SPI.
 
119 Exterior Shearwall
Cancelled
04/21/26
IVRUser
 
 
119 Exterior Shearwall
Reviewed
04/29/26
AEParrish
First floor exterior shear nailing and strapping, starting at grid lines D&8 to D&1 to A&1 to A&14 to O&14, ok pending SPI.
 
119 Exterior Shearwall
Reviewed
05/08/26
AEParrish
First floor exterior nailing and strapping ok, except car port area.
 
119 Exterior Shearwall
Reviewed
05/28/26
AEParrish
2nd and 3rd floor exterior shear ok, except court yard and North West end between lines A and D ok pending SPI.
 
119 Exterior Shearwall
Reviewed
06/03/26
AEParrish
Levels 2 & 3 court yard and NW corner (A -D), nailing and strapping ok pending SPI.
 
119 Exterior Shearwall
Reviewed
06/10/26
AEParrish
Level 4 exterior shear wall nailing and strapping grid lines A-D & line #1 (Northwest side), and line A, grid lines 1-14 (North side) ok pending SPI.
 
119 Exterior Shearwall
Reviewed
06/11/26
AEParrish
Level 4 exterior nailing and strapping ok pending SPI, except back side of building (East wall).
 
119 Exterior Shearwall
Reviewed
06/30/26
AEParrish
Level 5 exterior nailing and strapping ok.
 
119 Exterior Shearwall
Cancelled
07/24/26
IVRUser
 
 
119 Exterior Shearwall
Needed
   
 
129 Interior Shearwall
Cancelled
04/22/26
AEParrish
Cancelled, see floor sheathing.
 
129 Interior Shearwall
Reviewed
06/03/26
AEParrish
Interior shear wall nailing and Titan bolts on seal plates, grid lines A-D and 1-14.1 ok pending SPI.
 
129 Interior Shearwall
Reviewed
06/11/26
AEParrish
All of level 1 interior shear ok, pending SPI.
 
129 Interior Shearwall
Reviewed
07/15/26
AEParrish
Interior shear wall nailing for levels 2&3 ok, pending SPI.
 
129 Interior Shearwall
Cancelled
07/24/26
IVRUser
 
 
129 Interior Shearwall
Reviewed
07/29/26
AEParrish
Interior shear nailing for levels 4 and 5 ok pending SPI.
 
129 Interior Shearwall
Reviewed
08/04/26
AEParrish
Walked 5th floor and looked at A35 and DTT1Z brackets.
 
129 Interior Shearwall
Needed
   
 
120 Wall/Vault Insulation
Needed
   
 
130 Lath or Dry Wall
Reviewed
06/30/26
AEParrish
Two layers of Dens Glass for electrical chase from level 2 to level 5 on three sides of chase. Will need to verify fire caulking at all levels (penetrations) before closing up.
 
130 Lath or Dry Wall
Info Only
08/04/26
AEParrish
Just discussed sheet rock at top of elevator shaft and garbage chute.
 
130 Lath or Dry Wall
Needed
   
 
131 Firestop Assemblies
Needed
   
 
124 Final Insulation
Needed
   
 
146 Fire Sprinklers
Cancelled
06/02/26
ATBrushett
should have been underground
 
146 Fire Sprinklers
Reviewed
06/04/26
ATBrushett
Combination standpipe piping hydroed and installed up to the 3rd floor
 
146 Fire Sprinklers
Reviewed
08/05/26
ATBrushett
5th floor hydro and cover inspection. All OK except as noted below:
- Need to add CC heads to the corner areas with 6 inch truss
- Need to determine if the design allows no draft stopping (no draft stopping is required)
- Combustible deck in the hallways on other floors will need CC sprinklers. I believe its going to be required.
 
146 Fire Sprinklers
Needed
   
 
144 Emergency Generator
Needed
   
 
153 Water/Hydrant System
Reviewed
01/12/26
ATBrushett
6 inch underground OK to cover up to about 6ft from the vault. Vault still needs to be set. hydro flush and flow still needed
 
153 Water/Hydrant System
Reviewed
04/20/26
ATBrushett
Fire Line is complete from the vault to the building and the FDC is installed. Still need hydro flush and flow
 
153 Water/Hydrant System
Reviewed
06/02/26
ATBrushett
Flush and flow of the underground completed. 4 psi from the 4 1/2 hose monster need to find low flow chart to determine the flow. Hydro on the underground also complete.
 
153 Water/Hydrant System
Reviewed
06/04/26
ATBrushett
Forward flow produces 56psi from 1 1/8th hose monster 260 gpm. 2125 gpm required per the design so OK
 
153 Water/Hydrant System
Needed
   
 
154 Standpipe
Reviewed
08/05/26
ATBrushett
All of the standpipe has been hydroed and inspected. Just need to add bracing where it comes out of the riser room
 
154 Standpipe
Needed
   
 
143 Fire Regulation
Needed
   
 
150 Landscaping
Needed
  
Verify landscaping and irrigation.
 
919 Bicycle Parking
Needed
  
Verify long term bicycle parking spaces
 
157 Zoning
Needed
  
Verify pedestrian paths, pedestrian scale lighting, bumpers
 
160 Emerg Egress Light
Needed
   
 
199 Final Building
Needed
   
Electrical
Active
12/01/25
07/31/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
210 Undergrnd/Slab Elec
Reviewed
05/01/26
BARichardson
Underground for fire vault conduits
 
210 Undergrnd/Slab Elec
Needed
   
 
215 Electrical - Feeder
Info Only
06/24/26
JKGoschie
Reviewed feeder routes.
 
215 Electrical - Feeder
Needed
   
 
217 Electrical Service
Needed
   
 
213 Bonding/Grounding
Needed
   
 
225 Elec Ceiling Cover
Needed
   
 
220 Rough Electrical
Reviewed
06/24/26
JKGoschie
Electrical room West wall.
 
220 Rough Electrical
Reviewed
08/04/26
SRFitzHenry
fifth floor units ok
 
220 Rough Electrical
Needed
   
 
230 Limited Energy
Needed
   
 
255 Emergency Generator
Needed
   
 
299 Final Electrical
Needed
   
Fire
Active
12/01/25
07/31/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
849 Final Fire
Needed
   
Mechanical
Active
12/01/25
07/31/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
410 Underfloor Mechanical
Needed
   
 
416 Rough Gas Piping
Needed
   
 
450 Final Gas Piping
Needed
   
 
420 Rough Mechanical
Needed
   
 
499 Final Mechanical
Needed
   
Plumbing
Active
12/01/25
07/31/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
402 Sanitary Sewer - Private
Needed
   
 
403 Storm Sewer - Private
Reviewed
03/05/26
JSHemmele
2- 4" pvc lines stubbed into the northside of the court yard from building. on test. JSH
 
403 Storm Sewer - Private
Reviewed
03/06/26
JSHemmele
36' of 8" pvc from private side of manhole running north towards eweb vaults. JSH
 
403 Storm Sewer - Private
Reviewed
03/13/26
JSHemmele
2- 4" pvc lines in south building stubbed into court yard. JSH
 
403 Storm Sewer - Private
Needed
   
 
318 Under Floor Plumb
Reviewed
01/16/26
JSHemmele
From MH- 40' of 8" pvc and 80' of 6" pvc running north with y's cut in. test ok (deeps only) ok to cover. JSH
 
318 Under Floor Plumb
Reviewed
01/29/26
JSHemmele
East side of building up to 2 bedroom unit except kitchen drains under test. ok to cover. JSH
 
318 Under Floor Plumb
Reviewed
02/03/26
JSHemmele
Bike area north to janitors room. on test. ok to cover. JSH
 
318 Under Floor Plumb
Reviewed
02/11/26
JSHemmele
North end of building on test. Ok to cover. JSH
 
318 Under Floor Plumb
Reviewed
02/17/26
JSHemmele
South end of building on test. Ok to cover. cover parking drains to come. JSH
 
318 Under Floor Plumb
Reviewed
03/02/26
JSHemmele
AD's in parking area on test. Waiting for trap's and drains. ok to cover main lines. JSH
 
318 Under Floor Plumb
Not Needed
03/05/26
JSHemmele
Needed storm sewer inspection. JSH
 
320 Rough Plumbing
Cancelled
02/03/26
JSHemmele
Needed underfloor inspection. JSH
 
320 Rough Plumbing
Reviewed
07/17/26
JSHemmele
All waste on the north side except for showers. on test. JSH
 
320 Rough Plumbing
Reviewed
07/21/26
JSHemmele
Waste on the east side of building all 5 stories. on test. JSH
 
320 Rough Plumbing
Reviewed
07/23/26
JSHemmele
Waste is on test on the south side of hallway of the southside of building. JSH
 
320 Rough Plumbing
Reviewed
07/27/26
JSHemmele
All waste is done except rain drains and showers. JSH
 
320 Rough Plumbing
Needed
   
 
325 Water Service
Approved
04/29/26
JSHemmele
21/2" pex with tracer wire. Connected to pex that was already ran and continued running through backflow to meter. JSH
 
335 Backflow Device
Needed
   
 
399 Final Plumbing
Needed
   
Public Works
Active
12/01/25
07/31/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
401 Storm Sewer - Public
Reviewed
03/06/26
JRLaCasse
Use a City of Eugene fitting when connecting into the public manhole. Such as a Kor n seal boot or sanded MH adapter.
 
750 R/W Excavation
Needed
  
Connection into ST MH #64646
 
401 Storm Sewer - Public
Reviewed
03/09/26
JRLaCasse
Connection to Public manhole made via a sanded manhole adapter with tracer wire. Will final this after tracer wire is secured to inside the MH with a non-corrosive fastener.
 
401 Storm Sewer - Public
Needed
   
 
765 Sidewalk
Needed
  
Constructing setback sidewalk along both frontages - MLW x8485
 
799 Final Public Works
Needed
  
Verify that ADA ramp was not damaged. If damaged it must be repaired prior to CO. MLW x8485
To request an inspection go to https://pdd.eugene-or.gov/BuildingPermits/InspectionLogin.
For more information call 541-682-5283.
FEES
Fees
Total Due
Amount Paid
Paid Date
Amount Due
Application
$0.00
$0.00
 
$0.00
Miscellaneous Admin, State
$0.00
$0.00
12/01/25
$0.00
Building
$237,945.15
$234,858.04
 
$3,087.11
Addressing Fee for New Buildings
$47.90
$47.90
12/01/25
$0.00
Building Plan Check per Applicant Value
$51,143.78
$51,143.78
12/01/25
$0.00
Supplemental Plan Review, Bldg
$230.00
$230.00
12/01/25
$0.00
Supplemental Plan Review, Bldg
$1,926.25
$1,926.25
12/01/25
$0.00
Supplemental Plan Review, Bldg
$92.00
$92.00
01/30/26
$0.00
Supplemental Plan Review, Bldg
$23.00
$23.00
01/30/26
$0.00
Supplemental Plan Review, Bldg
$57.50
$57.50
03/27/26
$0.00
Supplemental Plan Review, Bldg
$57.50
$0.00
 
$57.50
Supplemental Plan Review, Bldg
$172.50
$0.00
 
$172.50
Supplemental Plan Check, Str. Eng.
$287.50
$287.50
12/01/25
$0.00
Supplemental Plan Check, Str. Eng.
$3,881.25
$3,881.25
12/01/25
$0.00
Supplemental Plan Check, Str. Eng.
$3,392.50
$3,392.50
12/01/25
$0.00
Supplemental Plan Check, Str. Eng.
$230.00
$230.00
12/01/25
$0.00
Supplemental Plan Check, Str. Eng.
$57.50
$57.50
01/30/26
$0.00
Supplemental Plan Check, Str. Eng.
$57.50
$57.50
01/30/26
$0.00
Supplemental Plan Check, Str. Eng.
$57.50
$57.50
01/30/26
$0.00
Supplemental Plan Check, Str. Eng.
$115.00
$115.00
01/30/26
$0.00
Supplemental Plan Check, Str. Eng.
$57.50
$57.50
01/30/26
$0.00
Supplemental Plan Check, Str. Eng.
$460.00
$460.00
01/30/26
$0.00
Supplemental Plan Check, Str. Eng.
$57.50
$57.50
01/30/26
$0.00
Supplemental Plan Check, Str. Eng.
$57.50
$57.50
01/30/26
$0.00
Supplemental Plan Check, Str. Eng.
$115.00
$115.00
03/27/26
$0.00
Supplemental Plan Check, Str. Eng.
$57.50
$0.00
 
$57.50
Supplemental Plan Check, Str. Eng.
$57.50
$0.00
 
$57.50
Fire/Life Safety Plan Check
$31,473.10
$31,473.10
12/01/25
$0.00
Fire Systems Plan Check Fee - Alarms
$687.38
$0.00
 
$687.38
Fire Systems Plan Check Fee - Sprinklers
$313.10
$313.10
01/30/26
$0.00
Fire Systems Plan Check Fee - Sprinklers
$1,440.58
$1,440.58
03/27/26
$0.00
Deferred Submittal Plan Check
$356.47
$356.47
01/30/26
$0.00
Deferred Submittal Plan Check
$230.00
$230.00
01/30/26
$0.00
Deferred Submittal Plan Check
$232.33
$0.00
 
$232.33
Deferred Submittal Plan Check
$257.96
$0.00
 
$257.96
Deferred Submittal Plan Check
$230.00
$0.00
 
$230.00
Building Permit Fee per Bldg Div Value
$78,682.74
$78,682.74
12/01/25
$0.00
Emergency Generator
$373.75
$373.75
03/27/26
$0.00
Erosion, Non-Permitted Site
$115.00
$115.00
12/01/25
$0.00
Fire System Permit Fee - Alarms
$1,057.50
$0.00
 
$1,057.50
Fire System Permit Fee - Sprinklers
$481.69
$481.69
01/30/26
$0.00
Fire System Permit Fee - Sprinklers
$2,216.28
$2,216.28
03/27/26
$0.00
Zoning Plan Check
$35,407.23
$35,407.23
12/01/25
$0.00
Supplemental Plan Review, Zoning
$57.50
$57.50
12/01/25
$0.00
Supplemental Plan Review, Zoning
$57.50
$0.00
 
$57.50
Supplemental Plan Review, Zoning
$34.50
$0.00
 
$34.50
Zoning Inspection
$345.00
$345.00
12/01/25
$0.00
State Surcharge, Structural
$9,697.62
$9,697.62
12/01/25
$0.00
State Surcharge, Structural
$57.80
$57.80
01/30/26
$0.00
State Surcharge, Structural
$310.80
$310.80
03/27/26
$0.00
State Surcharge, Structural
$126.90
$0.00
 
$126.90
Building Technology Admin Fee, Local
$4,144.40
$4,144.40
12/01/25
$0.00
Building Technology Admin Fee, Local
$48.33
$48.33
01/30/26
$0.00
Building Technology Admin Fee, Local
$84.06
$84.06
03/27/26
$0.00
Building Technology Admin Fee, Local
$58.04
$0.00
 
$58.04
Building Admin Fee, State
$2,068.66
$2,068.66
12/01/25
$0.00
Building Admin Fee, Local
$4.31
$4.31
12/01/25
$0.00
Building Plan Check Admin
$4,602.94
$4,602.94
12/01/25
$0.00
Building Plan Check Admin
$0.00
$0.00
 
$0.00
Electrical
$14,230.40
$14,230.40
 
$0.00
Electric Plan Check
$3,233.53
$3,233.53
12/01/25
$0.00
200 amps or less
$401.70
$401.70
12/01/25
$0.00
201 to 400 amps
$514.50
$514.50
12/01/25
$0.00
Over 1000 amps or volts
$753.00
$753.00
12/01/25
$0.00
Branch Circuits w/ Feeder or Service
$613.05
$613.05
12/01/25
$0.00
Wiring Footage, Each Add'l 500 sq ft
$6,675.90
$6,675.90
12/01/25
$0.00
Limited Energy, Multi-Family
$280.50
$280.50
12/01/25
$0.00
Generator Inspection
$351.00
$351.00
12/01/25
$0.00
State Surcharge, Electrical
$1,150.76
$1,150.76
12/01/25
$0.00
Electric Technology Admin Fee, Local
$256.46
$256.46
12/01/25
$0.00
Electric Admin Fee, State
$0.00
$0.00
12/01/25
$0.00
Electric Plan Check Admin
$0.00
$0.00
12/01/25
$0.00
Fire
$12,155.80
$12,097.15
 
$58.65
Fire Plan Check
$11,802.45
$11,802.45
12/01/25
$0.00
Supplemental Plan Review, Fire
$57.50
$57.50
03/27/26
$0.00
Supplemental Plan Review, Fire
$57.50
$0.00
 
$57.50
Fire Technology Admin Fee, Local
$236.05
$236.05
12/01/25
$0.00
Fire Technology Admin Fee, Local
$1.15
$1.15
03/27/26
$0.00
Fire Technology Admin Fee, Local
$1.15
$0.00
 
$1.15
Fire Plan Check Admin
$0.00
$0.00
12/01/25
$0.00
Fire Plan Check Admin
$0.00
$0.00
 
$0.00
Mechanical
$11,243.29
$11,243.29
 
$0.00
Mechanical Plan Check
$3,607.11
$3,607.11
12/01/25
$0.00
Supplemental Plan Review, Mechanical
$57.50
$57.50
12/01/25
$0.00
Supplemental Plan Review, Mechanical
$287.50
$287.50
12/01/25
$0.00
Mechanical Permit (Applicant Value)
$5,549.40
$5,549.40
12/01/25
$0.00
State Surcharge, Mechanical
$727.66
$727.66
12/01/25
$0.00
Mechanical Technology Admin Fee, Local
$190.03
$190.03
12/01/25
$0.00
Mechanical Plan Check Admin
$324.64
$324.64
12/01/25
$0.00
Mechanical Admin Fee, State
$499.45
$499.45
12/01/25
$0.00
Plumbing
$32,884.30
$32,884.30
 
$0.00
Plumbing Plan Check
$7,688.38
$7,688.38
12/01/25
$0.00
Plumbing Fixtures
$21,147.00
$21,147.00
12/01/25
$0.00
Sanitary Sewer Footage
$246.60
$246.60
12/01/25
$0.00
Storm Sewer Footage
$246.60
$246.60
12/01/25
$0.00
Water Service Footage
$212.60
$212.60
12/01/25
$0.00
Backflow Prevention
$57.00
$57.00
12/01/25
$0.00
Removal, Abandonment, Cap of Fixture
$57.00
$57.00
12/01/25
$0.00
State Surcharge, Plumbing
$2,636.02
$2,636.02
12/01/25
$0.00
Plumbing Technology Admin Fee, Local
$593.10
$593.10
12/01/25
$0.00
Plumbing Admin Fee, State
$0.00
$0.00
12/01/25
$0.00
Plumbing Plan Check Admin
$0.00
$0.00
12/01/25
$0.00
Public Works
$3,181.71
$3,123.06
 
$58.65
PW Plan Check, New Commercial
$1,270.00
$1,270.00
12/01/25
$0.00
Supplemental Plan Review, Public Works
$1,092.50
$1,092.50
12/01/25
$0.00
Supplemental Plan Review, Public Works
$57.50
$0.00
 
$57.50
Sidewalk, New Construction
$456.32
$456.32
12/01/25
$0.00
R-O-W Excavation (w/o pavement cuts)
$243.00
$243.00
12/01/25
$0.00
PW Technology Admin Fee, Local
$61.24
$61.24
12/01/25
$0.00
PW Technology Admin Fee, Local
$1.15
$0.00
 
$1.15
PW Plan Check Admin
$0.00
$0.00
12/01/25
$0.00
PW Plan Check Admin
$0.00
$0.00
 
$0.00
SDC
$724,200.81
$724,200.81
 
$0.00
Total All Fees
$1,035,841.46
$1,032,637.05
 
$3,204.41
System Development Charges By System
SDC Fees
Total Due
Amount Paid
Paid Date
Amount Due
City SDC Admin
$30,000.00
$30,000.00
 
$0.00
SDC City Admin
$30,000.00
$30,000.00
12/01/25
$0.00
City Wastewater
$72,949.17
$72,949.17
 
$0.00
RDU rate for calculation of local WW
$65,636.40
$65,636.40
12/01/25
$0.00
RDU rate for calculation of local WW
($1,640.91)
($1,640.91)
12/01/25
$0.00
Cost per SQFT local WWater living area
$9,303.88
$9,303.88
12/01/25
$0.00
Cost per SQFT local WWater living area
($350.20)
($350.20)
12/01/25
$0.00
Metropolitan Wastewater
$198,716.20
$198,716.20
 
$0.00
Single Family / Duplex
($5,970.01)
($5,970.01)
12/01/25
$0.00
Other Residential - Multi Family
$204,686.21
$204,686.21
12/01/25
$0.00
Parks
$394,194.23
$394,194.23
 
$0.00
Parks Single Family 800 sq ft or less
($3,645.42)
($3,645.42)
12/01/25
$0.00
Parks Mult-family 0 bedrooms
$206,113.05
$206,113.05
12/01/25
$0.00
Parks Multi-family 1 bedroom
$143,109.68
$143,109.68
12/01/25
$0.00
Parks Multi-family 2+ br w/in 1/4 mile
$56,719.74
$56,719.74
12/01/25
$0.00
Parks Multi-family 2+ br w/in 1/4 mile
($8,102.82)
($8,102.82)
12/01/25
$0.00
SDC Stormwater
$0.00
$0.00
 
$0.00
Impervious surface area
$4,855.58
$4,855.58
12/01/25
$0.00
Impervious surface area
($4,855.58)
($4,855.58)
12/01/25
$0.00
Transportation
$28,341.21
$28,341.21
 
$0.00
Trans Proximity 1/4 Mile
($20,751.39)
($20,751.39)
12/01/25
$0.00
Transportation Other credit
($1.00)
($1.00)
12/01/25
$0.00
Transportation Low Income Program Credit
($142,477.00)
($142,477.00)
12/01/25
$0.00
Miscellaneous (Transportation)
$207,513.91
$207,513.91
12/01/25
$0.00
Miscellaneous (Transportation)
($15,943.31)
($15,943.31)
12/01/25
$0.00
Total All SDC Fees
$724,200.81
$724,200.81
 
$0.00
Page 1 of 1
Date: 8/6/2026