City of Eugene
Planning & Development
Building and Permit Services
Permit Number: 25-04511-01
Date: 11/27/2026
Address: 1161 E 13TH AVE
Project Description: Deferred maintenance renovation including voluntary seismic upgrade.
Application Type:
Commercial
Status:
Issued
Scope of Work:
Phased Permit
Zoning:
Public Land
Map:
17-03-32-00
Tax Lot:
00100
Subdivision:
Addition:
Lot:
Block:
Date Received:
07/11/25
# Bedrooms:
0
Commitment Date:
09/08/25
# Dwelling Units:
0
Ready to issue as of:
05/14/26
In Flood Plain:
Project Coordinator:
Catherine R Allen
Phone:
541-682-6381
  
Sign Standards:
 
BUILDING CHARACTERISTICS
Construction Types:
3BS
Construction Type Comments:
 
OccupancyTypes:
B
 
Occupancy Type Comments:
S1
 
 
S2
 
 
Occupancy Load:
0
Separated Building:
N/A
Fire Sprinklers:
Yes Required
NFPA 13
Fire Alarms:
Yes Required
 
Building Area:
43323
Number of Stories:
4
Comment:
 
Floor Areas (sq ft):
Floor
Existing Floor Area
New Floor Area
Total Area
1st Floor
9999
826
10825
2nd Floor
8244
2596
10840
3rd Floor
6498
0
6498
4th Floor
5692
210
5902
Basement 1
7668
1413
9081
Existing floor area may not be shown.
CONTRACTOR DATA
Type
Contractor
Building
BREMIK CONSTRUCTION INC
Electric
ON ELECTRIC GROUP INC DBA OEG INC
Mechanical
ARCTIC SHEET METAL INC
Plumbing
ARCTIC SHEET METAL INC
Primary Contact
PEARRE JESSICA
PLAN REVIEW SUMMARY
Plan review data displayed is the most current for each review. The applicant will receive notification of all issues needing additional information after all reviews on a project have been completed. Supplemental Information (SI) can be submitted prior to or after permit issuance. If you have any questions regarding your project, contact CRAllen at 541-682-6381 or send email to Catherine.R.Allen@ci.eugene.or.us. Also note that some reviews (i.e., fire alarms, fire sprinklers) are deferred submittals and will be reviewed after original permit(s) have been issued.
Status Definitions
Pending
=
Review has not been started
Review
=
Under review
Waiting
=
Review for individual review has been completed, waiting for a response
External Wait
=
All reviews for project have been completed, waiting for a response
Approved
=
Review has been approved
Information
=
Information only, review not approved
Denied
=
Project cannot be approved as submitted
For information regarding the review of your project or the commitment date for completion of review, please contact your project coordinator, CRAllen, at Catherine.R.Allen@ci.eugene.or.us or by phone at 541-682-6381.
Plan Review
Status
Review Completion Date
Project Coordination, Application Submittal
Approved
09/09/25
Post Issuance Coord, Post Issuance SI
Approved
10/08/26
Deferred Coordination, Deferred Submittal
Approved
11/17/26
Building, Application Submittal
Approved
07/31/25
Building, Post Issuance SI
Approved
10/08/26
Structural, Application Submittal
Approved
07/24/25
Structural, Post Issuance SI
Approved
03/18/26
Structural, Deferred Submittal
Approved
07/30/26
Mechanical, Application Submittal
Information
07/14/25
Electrical, Application Submittal
Information
07/14/25
Plumbing, Application Submittal
Information
07/14/25
Zoning, Application Submittal
Information
08/29/25
Public Works, Application Submittal
Information
09/09/25
Fire Marshal, Application Submittal
Approved
09/04/25
Erosion Inspection, Application Submittal
Approved
10/03/25
Fire Sprinkler Plans, Deferred Submittal
Approved
11/12/26
Standpipe, Deferred Submittal
Approved
11/12/26
PERMITS AND INSPECTIONS
Permit Type
Status
 
Issued Date
Expiration Date
Completion Date
 
Building
Active
10/07/25
11/20/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
103 Footing
Cancelled
02/20/26
LODraper
Per the request of the contractor
 
103 Footing
Reviewed
03/19/26
FKamroyev
Shotcrete footings and vert at walls, West and East elevations @ GL: D.6-C.5 along line 0.1 and 2.3. South elevations full wall along GL: D.6. And elevator and pit footing and wall verts ok after SPI.
 
103 Footing
Reviewed
03/30/26
FKamroyev
Basement shotcrete footing and vert for walls @ GL C.5-C @ 2.6-2.3, A-B @ 2-2.5 at East wall and @ B-B.3 @ C.7-AA @ along line 01 at West wall, and 01-2.3 along line AA at North wall ok.
Elevator pit walls basement ok
Basement Interior shear wall verts ant its footings @ GL A-B.3 @ 01-1 and A-B.3 @ 2.3-2.5 ok.
 
103 Footing
Reviewed
05/07/26
FKamroyev
Northeast entry at basement ok
 
103 Footing
Reviewed
07/22/26
SEGalbreath
Partial for remaining step footings Building B South: Please address following 2 items before pouring:
1) Angled longitudinal top and bottom reinforcement not installed as shown on detail 10 on S5.01. This needs to be verified as done in special inspection report before approval can be given.
2) Due to change in step configuration top and bottom horizontal longitudinal bars with standard hooks do not extend through adjacent step and now terminate a few feet into adjacent step. Please provide documentation from E.O.R that this change is acceptable and that the as-built conditions are approvable.
 
103 Footing
No Access
09/23/26
LODraper
Site closed. OSSC Sec. 110.5
 
103 Footing
Reviewed
10/15/26
FKamroyev
Shotcrete walls levels 1-2 at C.5 @ 2.7 ok after SPI
 
103 Footing
Reviewed
11/24/26
FKamroyev
SE footings ok @ GL D.1-C.5 @ 2.3-3.3 after SPI approval
 
103 Footing
Needed
   
 
108 Foundation
Info Only
02/03/26
FKamroyev
Precon meeting
 
108 Foundation
Cancelled
02/19/26
AEParrish
Cancelled per contractor.
 
108 Foundation
Reviewed
04/06/26
FKamroyev
First floor complete
 
108 Foundation
Reviewed
05/04/26
FKamroyev
Perf pipe at basement ok
 
108 Foundation
Reviewed
08/31/26
FKamroyev
West tunnel walls ok
 
108 Foundation
Reviewed
11/24/26
FKamroyev
SE footings ok @ GL D.1-C.5 @ 2.3-3.3 after SPI approval
 
108 Foundation
Needed
   
 
110 Structural Concrete
Reviewed
04/27/26
FKamroyev
1893 basement ok
 
110 Structural Concrete
Reviewed
05/19/26
FKamroyev
NE basement mechanical room opening ok after SPI
 
110 Structural Concrete
Reviewed
05/21/26
FKamroyev
Level 1 shotcrete walls @ GL: AA.2.2-C-5 ok after SPI
 
110 Structural Concrete
Reviewed
05/27/26
FKamroyev
Shotcrete walls at level 1 West BLD ok
 
110 Structural Concrete
Reviewed
06/03/26
FKamroyev
Level 2 perimeter shotcrete walls ok.
 
110 Structural Concrete
Reviewed
06/05/26
FKamroyev
Rest of level 2 shotcrete walls including East bump out ok. Spoke w/ GC and SPI inspector in regards to bar spacing in between at added bar locations for shotcrete walls.
 
110 Structural Concrete
Reviewed
06/18/26
FKamroyev
SOG at 1914 BLD ok for pour
 
110 Structural Concrete
Reviewed
07/08/26
FKamroyev
Topping SOG at basement of 1893 ok
 
110 Structural Concrete
Reviewed
07/15/26
FKamroyev
Level 3 of 1893 BLD, perimeter shotcrete walls ok after SPI approval.
 
110 Structural Concrete
Reviewed
07/27/26
SEGalbreath
Contractor called/ forgot to schedule for 7/27. Shotcrete walls L4: (D .1-1.0), (C7 .1-1.0), (B3 .1-1.0), (A .1-1.0), (AA .1-2.3), (2.3 C.7-D). OK pending special inspections.
 
110 Structural Concrete
Reviewed
08/17/26
FKamroyev
Tunnel footing and verts ok
 
110 Structural Concrete
Reviewed
08/31/26
FKamroyev
West tunnel walls ok
 
110 Structural Concrete
Reviewed
09/09/26
FKamroyev
Shotcrete walls at BLD B basement and BLD C partial at elevator lobby ok after SPI
 
110 Structural Concrete
Reviewed
10/27/26
FKamroyev
Last interior shotcrete walls @ BLDs A, B and C ok after SPI
 
110 Structural Concrete
Reviewed
11/24/26
FKamroyev
SE footings ok @ GL D.1-C.5 @ 2.3-3.3 after SPI approval
 
110 Structural Concrete
Needed
   
 
118 Framing
Reviewed
08/03/26
FKamroyev
Basement lid floor framing, ok
 
118 Framing
Reviewed
08/31/26
FKamroyev
Walk through for stair #1 of stairs rise, height and uniformity. Code sections sent via text message. -FXK.
 
118 Framing
Reviewed
09/08/26
FKamroyev
Stairway 1 & 3 inspection: Stair treads and rise and walking surface slope shall be in compliance with OSSC 1011.5.4, 1011.5.2 and 1011.7.1. -FXK.
 
118 Framing
Reviewed
09/28/26
FKamroyev
Roof sheathing, strap and nailing inspection. Ok for cover.
 
118 Framing
Reviewed
10/01/26
FKamroyev
Most of basement steel stud framing ok pending other trades. Rated shaft walls remain.
 
118 Framing
Reviewed
11/24/26
FKamroyev
Level 1 stair #2 lobby framing ok. Fire-stopping needs to be address prior to full cover. Spoke w/ GC Brandon.
 
118 Framing
Needed
   
 
127 Masonry Construction
Needed
   
 
120 Wall/Vault Insulation
Needed
   
 
130 Lath or Dry Wall
Reviewed
08/20/26
FKamroyev
Structural beam drywall wrap at basement in progress, ok to wrap the rest
 
130 Lath or Dry Wall
Needed
   
 
131 Firestop Assemblies
Reviewed
09/11/26
FKamroyev
Fire-stopping at basement beam wrap areas, ok to continue.
 
131 Firestop Assemblies
Reviewed
09/21/26
FKamroyev
Drywall first layer progress at basement lid ok to continue
 
131 Firestop Assemblies
Reviewed
09/24/26
SEGalbreath
basement corridor lids in 2 areas before ductwork.
 
131 Firestop Assemblies
Reviewed
10/13/26
FKamroyev
Basement rate separation wall at MDF and electrical room, drywall ok. South side of basement spray foam insulation ok.
 
131 Firestop Assemblies
Reviewed
11/02/26
FKamroyev
F5 rated floor conditions at basement and rated shafts in progress at level 1 ok to continue
 
131 Firestop Assemblies
Reviewed
11/25/26
FKamroyev
Discussed level 1 stair-well and exit passageway location of not having any through penetrations. Walked basement for rated shafts, still in progress
 
131 Firestop Assemblies
Needed
   
 
121 Ceiling Grid
Needed
   
 
124 Final Insulation
Reviewed
11/25/26
FKamroyev
Basement thermal ok
 
124 Final Insulation
Needed
   
 
146 Fire Sprinklers
Needed
   
 
147 Alarm Systems
Needed
   
 
153 Water/Hydrant System
Needed
   
 
154 Standpipe
Needed
   
 
143 Fire Regulation
Needed
   
 
160 Emerg Egress Light
Needed
   
 
199 Final Building
Needed
   
Electrical
Active
05/14/26
11/20/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
210 Undergrnd/Slab Elec
Reviewed
09/29/26
JKGoschie
North of building.
 
210 Undergrnd/Slab Elec
Needed
   
 
215 Electrical - Feeder
Needed
   
 
217 Electrical Service
Cancelled
11/09/26
JKGoschie
 
 
217 Electrical Service
Reviewed
11/10/26
JKGoschie
Temp. service is approved.
 
217 Electrical Service
Needed
   
 
213 Bonding/Grounding
Reviewed
10/30/26
JKGoschie
Vault ground ring.
 
213 Bonding/Grounding
Needed
   
 
225 Elec Ceiling Cover
Needed
   
 
220 Rough Electrical
Cancelled
09/25/26
IVRUser
 
 
220 Rough Electrical
Reviewed
10/01/26
JKGoschie
Basement exterior walls.
 
220 Rough Electrical
Reviewed
11/20/26
JKGoschie
Basement area A.
 
220 Rough Electrical
Needed
   
 
230 Limited Energy
Reviewed
11/20/26
JKGoschie
Basement area A.
 
230 Limited Energy
Needed
   
 
299 Final Electrical
Needed
   
Fire
Active
10/07/25
11/20/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
849 Final Fire
Needed
   
Mechanical
Active
05/14/26
11/20/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
420 Rough Mechanical
Reviewed
09/28/26
FKamroyev
Basement supply duct, pressure test and duct seal ok.
 
420 Rough Mechanical
Reviewed
11/04/26
FKamroyev
Basement hydronic lines and testing ok. Spoke w/ installer, will call in each floor separately. -FXK.
 
420 Rough Mechanical
Needed
   
 
499 Final Mechanical
Needed
   
Plumbing
Active
05/14/26
11/20/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
402 Sanitary Sewer - Private
Approved
09/30/26
SEKelley
4" Sch. 40 PVC pumped waste from basement with tracer wire, tied into existing 3034 at Manhole.
 
403 Storm Sewer - Private
Reviewed
10/01/26
SEKelley
2 sticks of 6" 3034 with tracer wire, north side of building, west of sanitary manhole. Ok to cover.
 
403 Storm Sewer - Private
Needed
   
 
318 Under Floor Plumb
Cancelled
05/20/26
IVRUser
 
 
318 Under Floor Plumb
Reviewed
06/10/26
SEKelley
3" cast iron DWV, vent, CO, trap primer in Bldg. C, test ok, ok to cover.
 
318 Under Floor Plumb
Reviewed
06/22/26
SEKelley
Bldg. A underslab cast iron DWV and trap primers, elevator sump drain. Test ok, underfloor complete for Bldg. A.
 
318 Under Floor Plumb
Needed
   
 
320 Rough Plumbing
Reviewed
09/28/26
SEKelley
Basement level south of elevator shaft. Domestic hot, cold and return piping. Tests ok, ok to cover.
 
320 Rough Plumbing
Reviewed
10/06/26
RC Kennedy
Restroom and janitors closet, basement level in-wall rough H20 and DWV, test ok. Main floor level restrooms below floor piping DWV, test ok. South kitchenette basement level up to 1st floor, DWV-H20, test ok. RCK
 
320 Rough Plumbing
Reviewed
11/04/26
SEKelley
1st floor DWV and water tests ok, Rough plumbing complete on 1st floor.
 
320 Rough Plumbing
Needed
   
 
335 Backflow Device
Needed
   
 
399 Final Plumbing
Needed
   
Public Works
Active
10/07/25
11/20/27
  
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
725 Stormwater Mgmt Facility
Needed
   
 
735 Stormwater Facility Planting
Needed
   
 
799 Final Public Works
Needed
   
To request an inspection go to https://pdd.eugene-or.gov/BuildingPermits/InspectionLogin.
For more information call 541-682-5283.
FEES
Fees
Total Due
Amount Paid
Paid Date
Amount Due
Building
$58,973.70
$55,894.01
 
$3,079.69
Building Plan Check per Applicant Value
$14,442.57
$14,442.57
10/07/25
$0.00
Supplemental Plan Check, Str. Eng.
$57.50
$57.50
04/14/26
$0.00
Fire/Life Safety Plan Check
$8,887.74
$8,887.74
10/07/25
$0.00
Phased Permit Base Fee
$350.00
$350.00
10/07/25
$0.00
Phased Permit Coordination Fee
$1,500.00
$1,500.00
10/07/25
$0.00
Fire Systems Plan Check Fee - Sprinklers
$1,045.64
$0.00
 
$1,045.64
Deferred Submittal Plan Check
$230.00
$230.00
07/30/26
$0.00
Deferred Submittal Plan Check
$232.33
$0.00
 
$232.33
Building Permit Fee per Bldg Div Value
$22,219.34
$22,219.34
10/07/25
$0.00
Fire System Permit Fee - Sprinklers
$1,608.68
$0.00
 
$1,608.68
State Surcharge, Structural
$2,913.49
$2,913.49
10/07/25
$0.00
State Surcharge, Structural
$193.04
$0.00
 
$193.04
Building Technology Admin Fee, Local
$962.43
$962.43
10/07/25
$0.00
Building Admin Fee, State
$1,999.74
$1,999.74
10/07/25
$0.00
Building Admin Fee, State
$0.00
$0.00
04/14/26
$0.00
Building Plan Check Admin
$2,331.20
$2,331.20
10/07/25
$0.00
Building Plan Check Admin
$0.00
$0.00
04/14/26
$0.00
Building Plan Check Admin
$0.00
$0.00
07/30/26
$0.00
Building Plan Check Admin
$0.00
$0.00
 
$0.00
Fire
$3,699.47
$3,699.47
 
$0.00
Fire Plan Check
$3,332.85
$3,332.85
10/07/25
$0.00
Fire Technology Admin Fee, Local
$66.66
$66.66
10/07/25
$0.00
Fire Plan Check Admin
$299.96
$299.96
10/07/25
$0.00
Total All Fees
$62,673.17
$59,593.48
 
$3,079.69
Page 1 of 1
Date: 11/27/2026