PERMITS AND INSPECTIONS |
Permit Type | Status | | Issued Date | Expiration Date | Completion Date | |
Building | Active | 01/17/25 | 11/20/27 | | |
| | Inspection | Result | | Inspected | Inspector | Comment | |
| | 103 Footing | Reviewed | 02/24/25 | FKamroyev | 2nd phase of SE going West retaining wall footings per approved detail 30/S5.205 Ok after SPI approval. Previous corrections still apply to phase 1. Phase 1 poured w/o city approval, see previous memo. |
| | 103 Footing | Reviewed | 02/27/25 | LODraper | West end of south parking lot retaining wall footing reinforcement per approved plans. SPI pending. |
| | 103 Footing | Reviewed | 03/11/25 | LODraper | Inspection of tower crane footing reinforcement. This footing is not part of the building and not included in the approved drawings. The reinforcement at this location is per the drawings provided on site. OSSC Sec. 107.4 |
| | 103 Footing | Info Only | 03/24/25 | LODraper | Pre-construction walk w/Andrew and Compton (Hoffman). Contractor to submit SPI/load testing reports to the City for micropile installations. |
| | 103 Footing | Reviewed | 04/09/25 | LODraper | Column footings GL N.5/3.1, K-M/1.7-2.5 Continuous footing GL L/1.5-2.5 Columns not approved by COE. Z-bars at cont. ftg changed per RFI. These items are okay to pour per approval by the Building Official. SPI pending. |
| | 103 Footing | Reviewed | 04/11/25 | LODraper | Area B shear wall footings at lines N and 1.4, pile caps at lines 1.5 & 1.7 - shear walls and columns have not been approved by the COE at the time of inspection. Okay to pour these items per the Building Official. OSSC Sec. 107.4 |
| | 103 Footing | Denied | 04/18/25 | LODraper | Footings previously reviewed on 4-17-25 okay for concrete placement per the approval of the Building Official and pending SPI compliance. Sector B elevator footing not approved to pour. OSSC Sec. 107.4 |
| | 103 Footing | Reviewed | 04/21/25 | LODraper | Sector B elevator pit okay to pour per approval of BO and pending SPI compliance. |
| | 103 Footing | Reviewed | 04/28/25 | LODraper | Sectors A&B additional columns (3), column footings (6), and sump pump reinforcement ok to pour pending SPI compliance. See Inspector's map for specific locations. |
| | 103 Footing | Reviewed | 05/06/25 | LODraper | L0 sector A spread footing line K/6.5, sump footing, elevator 4 walls - ok to pour pending SPI compliance |
| | 103 Footing | Reviewed | 05/08/25 | LODraper | Sector A sump pit walls at line ~5.4 ok to pour w/SPI compliance. |
| | 103 Footing | Reviewed | 05/09/25 | LODraper | Pile caps (5) line Z/4.5-6 ok to pour pending SPI compliance. |
| | 103 Footing | Reviewed | 05/13/25 | LODraper | Sump footing line K.4/6.8 ok to pour pending SPI compliance. |
| | 103 Footing | Reviewed | 05/27/25 | LODraper | Sector B column footing GL 1.4/H.4, CIP wall footing line H.7 - ok to pour pending CPI compliance. |
| | 103 Footing | Cancelled | 06/12/25 | BUUnknown | |
| | 103 Footing | Reviewed | 06/17/25 | LODraper | Sector A IPF footing at GL 7 |
| | 103 Footing | Reviewed | 06/18/25 | LODraper | Southeast site wall and IPF footings in progress. |
| | 103 Footing | Reviewed | 06/25/25 | LODraper | L0 ne elevator core walls (3), sector C footings (4) GL 1.5/C-G. Additional east site wall footings/walls. SPI pending. |
| | 103 Footing | Reviewed | 07/10/25 | LODraper | East connector footings. IPF 5 footing. SPI pending. |
| | 103 Footing | Reviewed | 07/14/25 | LODraper | Wall at line 1.5, M, & Z.1. SPI pending. |
| | 103 Footing | Reviewed | 07/23/25 | LODraper | Sector B slab on grade in progress |
| | 103 Footing | Reviewed | 08/18/25 | LODraper | North shotcrete wall at existing basalt wall GL 5.5-10, additional se site walls |
| | 103 Footing | Reviewed | 09/10/25 | LODraper | Sector A slab on grade reinforcement per plan. SPI pending. |
| | 103 Footing | Reviewed | 09/11/25 | LODraper | SW IPF footings, NW IPF wall reinforcement per plan. SPI pending. |
| | 103 Footing | Reviewed | 10/01/25 | LODraper | L1 sector C deck okay for concrete placement pending SPI compliance. |
| | 103 Footing | Reviewed | 10/07/25 | LODraper | L1 deck pour 5 reinforcement in progress |
| | 103 Footing | Reviewed | 11/06/25 | LODraper | L1 south connector entry slab reinforcement per plan. SPI pending. |
| | 103 Footing | Reviewed | 12/10/25 | LODraper | Reinforcement for (2) south net wall pile caps per detail 8 on sheet S5.206. SPI pending |
| | 103 Footing | Reviewed | 01/26/26 | LODraper | Terraced concrete steps ok w/SPI compliance report |
| | 103 Footing | Reviewed | 02/02/26 | RZSteiner | connection slab for sloped spectator seating area near line 1.25 S.E. Needs follow up |
| | 103 Footing | Reviewed | 02/09/26 | LODraper | East site terrace stair reinforcement ok |
| | 103 Footing | Reviewed | 02/13/26 | LODraper | East site terrace steps reinforcement |
| | 103 Footing | Reviewed | 03/05/26 | LODraper | East of outdoor field stairs reinforcement |
| | 103 Footing | Reviewed | 04/14/26 | LODraper | South site goal post footings |
| | 103 Footing | Reviewed | 04/29/26 | LODraper | IPF column base encasement reinforcement per plan at 4 locations GL A.5 & H.5/3-4. SPI pending |
| | 103 Footing | Needed | | | |
| | 105 Elec Rebar Ground | Cancelled | 01/28/26 | LODraper | See masonry construction |
| | 105 Elec Rebar Ground | Needed | | | |
| | 108 Foundation | Denied | 02/20/25 | FKamroyev | Retaining wall at SE perimeter does not match approved detail 30/S5.205. On-site proposed EOR design changes need to be submitted for city review. OSSC 107.4 |
| | 108 Foundation | Reviewed | 02/24/25 | FKamroyev | 2nd phase of SE going West retaining wall footings per approved detail 30/S5.205 Ok after SPI approval. Previous corrections still apply to phase 1. Phase 1 poured w/o city approval, see previous memo. |
| | 108 Foundation | Reviewed | 04/09/25 | LODraper | Column footings GL N.5/3.1, K-M/1.7-2.5 Continuous footing GL L/1.5-2.5 Columns not approved by COE. Z-bars at cont. ftg changed per RFI. These items are okay to pour per approval by the Building Official. SPI pending. |
| | 108 Foundation | Reviewed | 04/24/25 | LODraper | Sector B elevator pit walls, various columns, L0 cip wall line L/1.5-2.5, sump pit - ok to pour pending SPI compliance. |
| | 108 Foundation | Reviewed | 04/29/25 | LODraper | Sector B additional columns and CIP wall reinforcement ok to pour pending SPI compliance. See map for approved items |
| | 108 Foundation | Reviewed | 04/30/25 | LODraper | Sector B strip footing GL 4.7, sector C elevator 4 pit footing - OK to pour pending SPI compliance. |
| | 108 Foundation | Reviewed | 05/01/25 | LODraper | L0 columns (2) line EX2/L-M ok to pour w/SPI compliance. L0 flood wall at line ~3.65 needs clarification for reinforcement details at openings. OSSC Sec. 107.4 |
| | 108 Foundation | Reviewed | 05/02/25 | LODraper | L0 sector B additional columns (9) ok to pour pending SPI compliance. See map for locations |
| | 108 Foundation | Reviewed | 05/07/25 | LODraper | L0 flood wall line M/3.65-4.6 ok to pour w/SPI compliance. |
| | 108 Foundation | Cancelled | 05/13/25 | LODraper | See footing. |
| | 108 Foundation | Reviewed | 06/02/25 | LODraper | L0 sector A shear wall footings at GL 5.5 and M in progress. Not per plan at this time, additional bar required. OSSC Sec. 107.4 |
| | 108 Foundation | Reviewed | 06/05/25 | LODraper | IPF footings in progress |
| | 108 Foundation | Reviewed | 06/06/25 | LODraper | IPF footings GL H.7/~3.6-5.2, shear wall H.7/1.7-2.5 - ok to pour pending SPI compliance. |
| | 108 Foundation | Reviewed | 06/09/25 | LODraper | L0 sector B shear walls GL 1.4 & N - ok to pour pending SI compliance |
| | 108 Foundation | Reviewed | 06/10/25 | LODraper | L0 sector B grade beams/footings GL 1 - ok to pour pending SPI compliance. |
| | 108 Foundation | Reviewed | 06/17/25 | LODraper | Sector A columns, footings at GL 1 |
| | 108 Foundation | Reviewed | 06/20/25 | LODraper | Se site wall footings |
| | 108 Foundation | Reviewed | 06/24/25 | LODraper | Courtesy inspection of HDPE condenser water piping on test at line 3.6. Current pressure observed at ~80 psi both lines. These plans have not been approved yet and the current installation is part of a revision to route these lines underground. OMSC Sec. 106.4.1 |
| | 108 Foundation | Reviewed | 06/27/25 | RZSteiner | Three C10 columns 1 line G.8-H |
| | 108 Foundation | Reviewed | 06/30/25 | LODraper | L0 sector A walls at lines 5.5 & M, sector B wall line H.7 |
| | 108 Foundation | Reviewed | 07/02/25 | LODraper | L0 shear walls at lines H and 5.5 |
| | 108 Foundation | Reviewed | 07/09/25 | LODraper | Additional line z cont. ftg., line 1 wall/columns, line 7 north columns (2). SPI pending. |
| | 108 Foundation | Reviewed | 07/10/25 | LODraper | West side condenser piping (2) from mechanical yard to IPF and expansion joint on test holding at 100 psi each. |
| | 108 Foundation | Reviewed | 07/15/25 | LODraper | L0 shear wall at line 2 in progress |
| | 108 Foundation | Reviewed | 07/21/25 | LODraper | East side connector-site wall footing, additional z line stem wall |
| | 108 Foundation | Reviewed | 07/25/25 | LODraper | L4 player's lounge curbs/pilasters, L0 sector B slab on grade, L0 line 1.5 connector wall. SPI pending. |
| | 108 Foundation | Reviewed | 08/05/25 | LODraper | Line Z SOG, columns, &. ftgs. Additional se IPF wall in progress |
| | 108 Foundation | Reviewed | 08/20/25 | LODraper | All remaining underground condenser water piping on test holding at or above 1.5x working pressure |
| | 108 Foundation | Reviewed | 09/09/25 | LODraper | L1 deck pour 1, sector A slab on grade in progress |
| | 108 Foundation | Reviewed | 09/24/25 | LODraper | L1 deck pour 3 ok pending SPI compliance. |
| | 108 Foundation | Reviewed | 09/30/25 | RZSteiner | Precast stair walls at ground level 2.5 line. Two center walls remain. |
| | 108 Foundation | Reviewed | 10/03/25 | LODraper | L1 deck pour 4 (sector B) okay for concrete placement pending SPI compliance. |
| | 108 Foundation | Reviewed | 10/08/25 | LODraper | Line 10 footing reinforcement okay to pour pending SPI compliance. |
| | 108 Foundation | Reviewed | 10/30/25 | LODraper | HDC building SOG reinforcement per plan. SPI pending. |
| | 108 Foundation | Reviewed | 11/03/25 | RZSteiner | Zone 4 SOG level 0 pending SPI |
| | 108 Foundation | Cancelled | 11/05/25 | LODraper | Will reschedule when housekeeping pads are ready. OSSC Sec. 110.5 |
| | 108 Foundation | Reviewed | 12/04/25 | LODraper | South side net wall pier footings reinforcement per plan. SPI pending. Multiple SPI compliance reports have been reviewed and accepted related to the compressive strength requirements being met for portions of the scope of this work. |
| | 108 Foundation | Reviewed | 12/15/25 | LODraper | NOLR SOMD pour 2, se net wall reinforcement okay for concrete placement w/SPI compliance |
| | 108 Foundation | Cancelled | 12/24/25 | BUUnknown | |
| | 108 Foundation | Cancelled | 02/03/26 | LODraper | See foundation |
| | 108 Foundation | Reviewed | 02/17/26 | LODraper | Se corner site grade beam reinforcement |
| | 108 Foundation | Needed | | | |
| | 109 Foundation Drain/Waterproofing | Cancelled | 06/23/25 | LODraper | Preliminary walk through of initial condenser water installation. Not under test. Will reschedule when ready. |
| | 109 Foundation Drain/Waterproofing | Needed | | | |
| | 110 Structural Concrete | Reviewed | 02/28/25 | LODraper | 1st section of retaining wall reinforcement at south parking lot ok to pour pending SPI compliance. Ref. RFI #339 |
| | 110 Structural Concrete | Reviewed | 03/11/25 | LODraper | South parking lot retaining wall reinforcement per plan. |
| | 110 Structural Concrete | Reviewed | 04/09/25 | LODraper | Column footings GL N.5/3.1, K-M/1.7-2.5 Continuous footing GL L/1.5-2.5 Columns not approved by COE. Z-bars at cont. ftg changed per RFI. These items are okay to pour per approval by the Building Official. SPI pending. |
| | 110 Structural Concrete | Reviewed | 04/11/25 | LODraper | Area B shear wall footings at lines N and 1.4, pile caps at lines 1.5 & 1.7 - shear walls and columns have not been approved by the COE at the time of inspection. Okay to pour these items per the Building Official. OSSC Sec. 107.4 |
| | 110 Structural Concrete | Reviewed | 04/17/25 | LODraper | Area B spread footings GL 3.7-4.5/K-M, shear wall footing GL 3.65/J.2-M. Vertical elements not approved. Okay to pour these footings per BO and pending SPI compliance. OSSC Sec. 107.4 |
| | 110 Structural Concrete | Reviewed | 04/21/25 | LODraper | Sector B elevator pit footing okay to pour per approval of BO and pending SPI compliance. |
| | 110 Structural Concrete | Reviewed | 05/14/25 | LODraper | Sector B flood wall line P/4.5 ok to pour pending SPI approval. |
| | 110 Structural Concrete | Reviewed | 05/15/25 | LODraper | Sector B sump walls line K/6.65, grease interceptor footing sector B - ok to pour pending SPI compliance. |
| | 110 Structural Concrete | Reviewed | 05/16/25 | LODraper | HDC wall at existing building per detail 4 on sheet S6.300 per plan. Ok to pour pending SPI compliance. |
| | 110 Structural Concrete | Reviewed | 05/19/25 | LODraper | L0 sector B south of flood wall column footings (5) ok to pour pending SPI compliance. See map for specific locations. |
| | 110 Structural Concrete | Reviewed | 05/21/25 | LODraper | Sector A sump walls GL 9/J, pile caps (2) lines 6.5/7, and column reinforcement (5) at column footings inspected during last inspection. |
| | 110 Structural Concrete | Reviewed | 05/23/25 | LODraper | L0 sector B shear wall footing GL H.7 in progress |
| | 110 Structural Concrete | Reviewed | 05/28/25 | LODraper | Practice facility - north continuous footing GL Z.1, South parking - west site wall footing - ok to pour pending SPI compliance. |
| | 110 Structural Concrete | Reviewed | 05/29/25 | LODraper | In progress bottom mat inspection of IPF footings zone B. There are plan sheets related these footings that do not appear to be approved. OSSC Sec. 107.4 |
| | 110 Structural Concrete | Reviewed | 05/30/25 | LODraper | Same shear wall footing in progress |
| | 110 Structural Concrete | Reviewed | 06/02/25 | LODraper | L0 sector A shear wall footings at GL 5.5 and M in progress. Not per plan at this time, additional bar required. OSSC Sec. 107.4 |
| | 110 Structural Concrete | Reviewed | 06/03/25 | LODraper | IPF footings in progress |
| | 110 Structural Concrete | Reviewed | 06/04/25 | LODraper | IPF footings in progress. L0 sector A columns (4) ok to pour pending SPI compliance. |
| | 110 Structural Concrete | Reviewed | 06/13/25 | LODraper | Sector B IPF footing, east continuous footings - ok to pour pending SPI compliance |
| | 110 Structural Concrete | Reviewed | 06/17/25 | LODraper | Sector A columns, footings at GL 1 |
| | 110 Structural Concrete | Reviewed | 06/23/25 | LODraper | Additional sector A and B columns, IPF footing, and wall. SPI pending. |
| | 110 Structural Concrete | Reviewed | 06/24/25 | LODraper | L0 sector B additional column footings line H.9, additional se site wall reinforcement. SPI pending. |
| | 110 Structural Concrete | Reviewed | 06/26/25 | RZSteiner | IPF footing Sector D Line 3-4.5 Between A-B. Sector C8 columns along line 1.5. Elevator shaft walls not ready.
|
| | 110 Structural Concrete | Reviewed | 07/03/25 | LODraper | Z line continuous footing in progress |
| | 110 Structural Concrete | Reviewed | 07/07/25 | LODraper | Sector B SOG east of line 3.7 |
| | 110 Structural Concrete | Reviewed | 07/11/25 | LODraper | Ne IPF wall, additional east site walls, sector A columns (3), and spread footings (2) at IPF ftgs line 6/7. SPI pending. |
| | 110 Structural Concrete | Reviewed | 07/14/25 | LODraper | Walls at lines 1.5, M, & Z.1. SPI pending. |
| | 110 Structural Concrete | Reviewed | 07/18/25 | LODraper | L0 sector C connector walls at lines 2 & B. SPI pending. |
| | 110 Structural Concrete | Reviewed | 07/29/25 | LODraper | Connector-site wall reinforcement |
| | 110 Structural Concrete | Reviewed | 08/01/25 | LODraper | Additional sector A columns, se IPF wall in progress, line 7.5 shear wall footing in progress. |
| | 110 Structural Concrete | Reviewed | 08/05/25 | LODraper | Line Z SOG, columns, &. ftgs. Additional se IPF wall in progress |
| | 110 Structural Concrete | Reviewed | 08/06/25 | LODraper | Additional se IPF wall reinforcement okay to pour pending SPI compliance |
| | 110 Structural Concrete | Reviewed | 08/08/25 | LODraper | Additional site wall reinforcement per plan. |
| | 110 Structural Concrete | Reviewed | 08/11/25 | RZSteiner | 7.5 shear wall 1st level pending SPI. |
| | 110 Structural Concrete | Reviewed | 08/15/25 | LODraper | Nw IPF footing, ne slab on grade (5"). SPI pending. |
| | 110 Structural Concrete | Reviewed | 08/21/25 | LODraper | Connector stair footings reinforcement per plan. SPI pending. |
| | 110 Structural Concrete | Reviewed | 08/26/25 | LODraper | Connector slab on grade reinforcement per plan. SPI pending. |
| | 110 Structural Concrete | Reviewed | 08/27/25 | LODraper | North IPF wall GL ~7.6-9.2 reinforcement per plan. SPI pending. |
| | 110 Structural Concrete | Reviewed | 08/29/25 | LODraper | Stair 19 wall in progress, remaining se site wall reinforcement per plan. |
| | 110 Structural Concrete | Reviewed | 09/02/25 | LODraper | Stair 19 wall and SOG at existing bldg adjacent to connector |
| | 110 Structural Concrete | Reviewed | 09/08/25 | LODraper | L1 deck pour 1 reinforcement in progress |
| | 110 Structural Concrete | Reviewed | 09/16/25 | LODraper | L1 deck pour 2 reinforcement in progress |
| | 110 Structural Concrete | Reviewed | 09/17/25 | LODraper | L1 deck pour 2 reinforcement okay for concrete placement pending SPI compliance. |
| | 110 Structural Concrete | Reviewed | 09/18/25 | LODraper | Sector A steel column footings GL 8-9.1 okay to pour w/SPI compliance |
| | 110 Structural Concrete | Reviewed | 09/23/25 | LODraper | Sector A classroom stairs stem walls, se site wall, and nw IPF wall reinforcement per plan. SPI pending. |
| | 110 Structural Concrete | Denied | 09/26/25 | FKamroyev | Beam on Y line called in for 8am inspection and poured without inspection prior to arrival. OSSC 110.5 Need SPI letter(s) and pictures or other documentation(s) to verify and proof for alternative way for inspection. In addition, need B/O approval. |
| | 110 Structural Concrete | Reviewed | 09/29/25 | FKamroyev | Pool rebar at sectors A-B level 1 Lower deck rebar at sector A SouthEast and South line beam top of shear walls at sector C ok after SPI |
| | 110 Structural Concrete | Reviewed | 10/02/25 | LODraper | L1 north sector B deck in progress, SW IPF wall ok w/SPI compliance, stair 19 north and south walls ok |
| | 110 Structural Concrete | Reviewed | 10/07/25 | LODraper | L1 deck pour 4 final. SPI pending |
| | 110 Structural Concrete | Reviewed | 10/10/25 | LODraper | SW IPF wall reinforcement line 9-10 ok pending SPI compliance |
| | 110 Structural Concrete | Reviewed | 10/14/25 | LODraper | L1 deck pour 6 reinforcement in progress, L1 sector A beams at lines Y & Z ok pending SPI compliance. |
| | 110 Structural Concrete | Reviewed | 10/22/25 | LODraper | L1 deck pour 5 and sw IPF wall reinforcement. SPI pending. |
| | 110 Structural Concrete | Reviewed | 10/23/25 | LODraper | L0 line 10 flood wall reinforcement per plan. SPI pending. |
| | 110 Structural Concrete | Reviewed | 11/04/25 | RZSteiner | IPF wall S.E. 4-5 pending SPI |
| | 110 Structural Concrete | Reviewed | 11/19/25 | LODraper | L0 slab pour back and stem walls pool equipment area, L4 bathroom and ramp SOMD north of outdoor kitchen - reinforcement at these location per plan. SPI pending. |
| | 110 Structural Concrete | Denied | 11/20/25 | LODraper | Connector SOG reinforcement per plan. SPI pending. L0 column reinforcement at GL ~5.5/K not on COE approved drawings. OSSC Sec. 107.4 |
| | 110 Structural Concrete | Reviewed | 11/25/25 | LODraper | West IPF perimeter stemwalls, sector A housekeeping pads. SPI pending |
| | 110 Structural Concrete | Reviewed | 12/01/25 | LODraper | L0 north electrical room walls, stair 19 walls, L4 connector SOMD - all reinforcement per plan. SPI pending |
| | 110 Structural Concrete | Reviewed | 12/03/25 | LODraper | Additional housekeeping pads, south connector electrical room walls, classroom stairs - SPI pending |
| | 110 Structural Concrete | Reviewed | 12/11/25 | LODraper | Level 2M SOMD pour 1 reinforcement okay pending SPI compliance |
| | 110 Structural Concrete | Reviewed | 12/12/25 | LODraper | 2 additional net wall pile caps at the southwest area. SPI pending |
| | 110 Structural Concrete | Reviewed | 12/18/25 | LODraper | Connector roof SOMD reinforcement per plan. SPI pending |
| | 110 Structural Concrete | Reviewed | 12/22/25 | LODraper | Additional south end net wall reinforcement per plan. SPI pending |
| | 110 Structural Concrete | Cancelled | 12/29/25 | RZSteiner | Wrong Insp/ code |
| | 110 Structural Concrete | Reviewed | 01/05/26 | LODraper | NOLR slab pour 3 ok w/SPI compliance |
| | 110 Structural Concrete | Reviewed | 01/07/26 | LODraper | Additional south side net wall reinforcement for pour 3 per plan. SPI pending |
| | 110 Structural Concrete | Reviewed | 01/12/26 | LODraper | Stair 14 L1-L3 SOMD landings, connector roof curbs, and sw net wall reinforcement per plan. SPI pending |
| | 110 Structural Concrete | Reviewed | 01/21/26 | LODraper | NOLR roof SOMD reinforcement per plan. SPI pending |
| | 110 Structural Concrete | Reviewed | 01/26/26 | LODraper | NOLR level 2M deck pour 4 reinforcement ok for concrete placement pending SPI compliance |
| | 110 Structural Concrete | Reviewed | 01/29/26 | LODraper | NOLR level 2M mechanical pads, roof level sector A curbs reinforcement per plan. SPI pending |
| | 110 Structural Concrete | Reviewed | 02/11/26 | LODraper | L0 at HDC existing parking garage area - shear wall modification reinforcement at GL EX2/EFG-EFH. SPI pending |
| | 110 Structural Concrete | Reviewed | 02/13/26 | LODraper | Connector LVL 4 N side SOMD, storage & electrical room roofs SOMD, level 1 along 2.5 line. 7.5-7.9 line SOMD level 1. Stairs 13 & 22. SPI pending |
| | 110 Structural Concrete | Reviewed | 02/19/26 | LODraper | NOLR level 1 radiant slab ok to pour pending SPI compliance |
| | 110 Structural Concrete | Reviewed | 04/23/26 | LODraper | Stairs 19/23, level 1 line 1 curb reinforcement |
| | 110 Structural Concrete | Reviewed | 06/11/26 | LODraper | Reinforcement at IPF column base encasements, 4 more locations |
| | 110 Structural Concrete | Reviewed | 08/07/26 | LODraper | 4 additional column base encasements, 7-10 |
| | 110 Structural Concrete | Reviewed | 09/24/26 | LODraper | L0 wall GL M/3.5-3.6. SPI pending |
| | 110 Structural Concrete | Needed | | | |
| | 118 Framing | Cancelled | 12/08/25 | LODraper | See masonry construction. |
| | 118 Framing | Info Only | 01/22/26 | LODraper | Framing pre-construction walk. Spoke to the contractor about the need for rough-in approvals prior to framing cover approval and various firestopping requirements at fire rated walls. |
| | 118 Framing | Reviewed | 02/17/26 | LODraper | NOLR north elevation exterior CFS framing, L4 connector above player's lounge eyebrow CFS framing |
| | 118 Framing | Reviewed | 02/26/26 | LODraper | NOLR north elevation sheathing (glass roc) attachments per the MII |
| | 118 Framing | Reviewed | 03/18/26 | LODraper | L1 east half locker room top-out |
| | 118 Framing | Reviewed | 03/30/26 | LODraper | NOLR west wall GL 8 |
| | 118 Framing | Reviewed | 04/03/26 | LODraper | Coach's office/bathroom/marshall's office okay for ceiling cover w/rough-in approvals |
| | 118 Framing | Reviewed | 04/13/26 | LODraper | L1 west locker room, L2M south and east mechanical area exterior walls |
| | 118 Framing | Reviewed | 04/17/26 | LODraper | HDC level 1 office 104, HDC level 1 The Loop east and south walls, L2M conference room |
| | 118 Framing | Reviewed | 04/23/26 | LODraper | Duck walk CFS, Stair 14 south exterior wall levels 1-4, level 0 drying room area - no cover at cmu rated walls yet, firestopping required. OSSC Sec. 107.4 |
| | 118 Framing | Cancelled | 05/06/26 | LODraper | See insulation |
| | 118 Framing | Reviewed | 05/13/26 | LODraper | NOLR classroom ceiling framing ok |
| | 118 Framing | Reviewed | 05/26/26 | LODraper | NOLR level 1 west locker room pod, shower & toilet room area |
| | 118 Framing | Reviewed | 06/05/26 | LODraper | L1 north connector walls, L1 east locker room pod drop ceilings |
| | 118 Framing | Reviewed | 06/15/26 | LODraper | NOLR level 1 west locker room pod ceilings, nw bathroom area, and sw of locker room bathroom and adjacent rooms |
| | 118 Framing | Reviewed | 06/22/26 | RZSteiner | Shaft lid and wall framing level 0 sector C and level 1 sector A |
| | 118 Framing | Reviewed | 07/15/26 | LODraper | L1A and L4C bathroom and north utility rooms. No above ceiling cover yet at L4C north where rated walls occur. |
| | 118 Framing | Reviewed | 08/13/26 | LODraper | SW classroom furred wall, AV room perimeter, east of locker room ceiling, pool shower ceiling, locker room ceiling |
| | 118 Framing | Reviewed | 08/24/26 | LODraper | East side connector eyebrow framing ok |
| | 118 Framing | Cancelled | 09/18/26 | LODraper | Contractor not on site, no response to phone call. |
| | 118 Framing | Reviewed | 09/22/26 | LODraper | Sports performance, classroom, treadmill pool ceilings. Stair 14 walls |
| | 118 Framing | Reviewed | 10/16/26 | LODraper | L0-L4 elevator 5 fronts |
| | 118 Framing | Needed | | | |
| | 127 Masonry Construction | Reviewed | 09/24/25 | LODraper | Cmu mockup core samples reviewed per the request by Victor from Hoffman Construction. Precon conducted with Victor and the masonry foreman regarding required city and special inspections. |
| | 127 Masonry Construction | Reviewed | 11/18/25 | LODraper | L0-L1 sector C east side cmu walls at lines 2 & E ok to grout pending SPI compliance. Ref. RFI #669 |
| | 127 Masonry Construction | Reviewed | 11/24/25 | LODraper | Sports performance/medical and nutrition storage rooms full height cmu walls ok to grout pending SPI compliance. |
| | 127 Masonry Construction | Reviewed | 12/03/25 | LODraper | L0 connector cmu walls |
| | 127 Masonry Construction | Reviewed | 12/08/25 | LODraper | L0 sector C toilet rm, custodial, service corridor cmu walls. SPI pending. |
| | 127 Masonry Construction | Reviewed | 12/11/25 | LODraper | L0 connector additional cmu walls okay to grout pending SPI compliance |
| | 127 Masonry Construction | Reviewed | 12/16/25 | LODraper | Additional cmu walls at L0 ok to grout w/SPI compliance |
| | 127 Masonry Construction | Reviewed | 12/19/25 | LODraper | Additional L0 sector C cmu walls. SPI pending |
| | 127 Masonry Construction | Reviewed | 12/29/25 | RZSteiner | Ground 0 CMU around chiller room see A3.100B for location. Pending SPI |
| | 127 Masonry Construction | Reviewed | 01/06/26 | LODraper | L0 lobby, sports performance, nutrition storage area cmu walls. SPI pending |
| | 127 Masonry Construction | Reviewed | 01/12/26 | LODraper | L0 additional cmu walls okay for grout w/SPI compliance |
| | 127 Masonry Construction | Reviewed | 01/16/26 | LODraper | L0 sector B additional cmu walls. SPI pending |
| | 127 Masonry Construction | Reviewed | 01/22/26 | LODraper | Additional cmu walls at L0 sector B pool storage and electrical rooms. SPI pending |
| | 127 Masonry Construction | Reviewed | 01/26/26 | LODraper | L0 sector B additional cmu walls. SPI pending |
| | 127 Masonry Construction | Reviewed | 01/28/26 | LODraper | L0 sector B additional cmu walls ok for grout w/SPI compliance |
| | 127 Masonry Construction | Reviewed | 02/03/26 | LODraper | L0 sector A cmu walls at heating plant, service corridor, and electrical room areas. SPI pending |
| | 127 Masonry Construction | Reviewed | 02/09/26 | LODraper | L0 sector A additional cmu walls ok to grout pending SPI compliance |
| | 127 Masonry Construction | Reviewed | 02/12/26 | LODraper | L0 sector A cmu wall reinforcement. SPI pending |
| | 127 Masonry Construction | Reviewed | 02/18/26 | LODraper | L0 sector A cmu walls' reinforcement per plan. SPI pending |
| | 127 Masonry Construction | Reviewed | 02/23/26 | LODraper | L0 sector C additional cmu walls north of bathroom/laundry area. SPI pending |
| | 127 Masonry Construction | Needed | | | |
| | 120 Wall/Vault Insulation | Reviewed | 05/06/26 | LODraper | NOLR level 2M at line Z |
| | 120 Wall/Vault Insulation | Reviewed | 06/05/26 | LODraper | L1 NOLR electrical room 146 south wall |
| | 120 Wall/Vault Insulation | Denied | 09/21/26 | LODraper | Contractor unavailable upon arrival onsite. Texts and calls conducted without a response while on site. OSSC Sec. 110.5 |
| | 120 Wall/Vault Insulation | Info Only | 11/24/26 | LODraper | A discussion with the framing foreman (Alex) regarding inspection requirements for the Oculus framing. It is okay to take pictures showing the connections and CFS gauge to verify that they match the plan details. OSSC Sec. 107.4 |
| | 120 Wall/Vault Insulation | Needed | | | |
| | 130 Lath or Dry Wall | Reviewed | 03/30/26 | LODraper | NOLR west wall GL 8 |
| | 130 Lath or Dry Wall | Reviewed | 04/16/26 | LODraper | Elevator 5 levels 1-4 first layer interior |
| | 130 Lath or Dry Wall | Reviewed | 05/01/26 | LODraper | L2M duck walk IPF wall, elevator 5 east wall 1st layer |
| | 130 Lath or Dry Wall | Reviewed | 05/06/26 | LODraper | Connector south exterior wall all levels (not fire-rated), 2nd layer in progress at elevator 5 |
| | 130 Lath or Dry Wall | Cancelled | 05/13/26 | LODraper | Not needed today |
| | 130 Lath or Dry Wall | Reviewed | 05/26/26 | LODraper | NOLR level 1 electrical room 146 south shaft wall and line 6.5 shaft wall core board, level 1-4 shaft wall adjacent to elevator 5 core board |
| | 130 Lath or Dry Wall | Reviewed | 06/05/26 | LODraper | L1 NOLR electrical room 146 south wall 1st layer, other walls at this room 1 layer ok |
| | 130 Lath or Dry Wall | Reviewed | 06/15/26 | LODraper | Stair 13 south shaft wall core board |
| | 130 Lath or Dry Wall | Reviewed | 06/22/26 | RZSteiner | Shaft lid and wall level 0 sector C and level 1 sector A |
| | 130 Lath or Dry Wall | Reviewed | 07/15/26 | LODraper | Stair 13 L1-L2M shaft core board |
| | 130 Lath or Dry Wall | Reviewed | 08/13/26 | LODraper | South connector elevator shaft 1st layer and stagger |
| | 130 Lath or Dry Wall | Reviewed | 09/22/26 | LODraper | Stair 14 walls exterior side |
| | 130 Lath or Dry Wall | Reviewed | 10/16/26 | LODraper | L0-L4 elevator 5 fronts shaftliner, L4 connector above lid at IDF room fire caulking |
| | 130 Lath or Dry Wall | Reviewed | 11/10/26 | LODraper | Barbershop walls, L0 lobby ceiling framing |
| | 130 Lath or Dry Wall | Needed | | | |
| | 131 Firestop Assemblies | Needed | | | |
| | 124 Final Insulation | Reviewed | 05/01/26 | LODraper | L2M NOLR west exterior walls. Connector south exterior wall |
| | 124 Final Insulation | Reviewed | 05/13/26 | LODraper | NOLR level 2M stair 13 exterior wall, east side mechanical room insulation and vapor barrier |
| | 124 Final Insulation | Needed | | | |
| | 146 Fire Sprinklers | Reviewed | 01/12/26 | ATBrushett | Piping for the 4 field level standpipes has been inspected and is ok to cover. Hydro on the piping for the standpipes OK. Wil need to flush the standpipe system once the system gets water. |
| | 146 Fire Sprinklers | Reviewed | 03/27/26 | ESPhillips-Meadow | Cover inspection Level 0 - Sector C & HDC Lanning Office:
Level 0 / sector C: Piping, bracing and heads & whips installed and ok to cover except as follows. 1. Lateral missing on hallway 6" line at ST3B 2. Clarify why the two longitudinal braces are not in place on the 6" in the hallway. 3. Provide lateral on 2.5" line in hallway at CM4S.
4th Floor Lanning Office: ok to cover. Send picture of last bracing in ceiling grid, or review in field later.
|
| | 146 Fire Sprinklers | Reviewed | 04/08/26 | ATBrushett | Hydro on the system that is fed from the existing building complete. still need to provide bracing to portions of the feed main closest to the riser |
| | 146 Fire Sprinklers | Reviewed | 05/06/26 | ATBrushett | Hydro and cover inspection for level zero wet system Electrical, Mechanical, and Pool area corrections needed noted below -Electrical room heads need to be below the fireproofing and there is an electrical box that is an obstruction -Conduit needs to be a min 3 inches from the sprinkler heads (hallway) -End of line restraint in the electrical room 046 and 047 -Need sprinkler under stairs -End of line restraint and finish main bracing in the under spa area and the pool equipment room -Level zero zero wet system electrical and mechanical pool area
|
| | 146 Fire Sprinklers | Reviewed | 05/19/26 | ATBrushett | Bulk feed and Level 1 cover and hydro completed items needing correction are listed below
-Level 1 loop bulk feed hydro North corridor needs longitudinal bracing and at the transition to the 4 inch Need 4 way Longitudinal at change in direction for east corner of parking garage Make sure torque off bolts are snapped off especially where the garage scrim is Add brace at 90 by the job lunch room South east corner at level 1 needs 4 way bracing at changes in direction Need to look at how far after change in direction for bracing
-Level 1 Class rooms need to have line restraint added Line restraint for branch line by stair Restraint at water treadmill Provide line restraint by PT 3 Add line restraint by electrical room for the 2 south branch lines Add restraint to middle of the south line level 1 Need to see what stretched fabric is and verify it will comply as a thermal barrier
|
| | 146 Fire Sprinklers | Reviewed | 05/29/26 | ATBrushett | cover and hydro inspection for the levels listed below, corrections needed are noted
Level 2 m sector c needs heads under hvac work over 4 feet hydro. Also need to verify the standpipe riser outlet will be available in the cabinet.
-Level 4 sector c wet system ok need bracing at seismic joint in new side -Also need to determine sprinklers for outdoor tv area -Bracing for the 4th floor risers needs to be added
|
| | 146 Fire Sprinklers | Reviewed | 06/05/26 | KAHaggas | Coach Lanning's Office inspected for occupancy: sprinklers, alarms, exits all ok, ok to occupy office. |
| | 146 Fire Sprinklers | Reviewed | 06/30/26 | ATBrushett | Corrections from the inspection on 5-29 have been made and re inspected. Cover and hydro for the 4th floor mechanical space OK |
| | 146 Fire Sprinklers | Reviewed | 08/14/26 | ESPhillips-Meadow | Hydro for Levell 4 and level 0 Dry systems at 220 PSI for 2 hrs. - OK Level 4 dry system (patio / kitchen) and Level 0 dry system (tunnel and parking piping and bracing): piping and bracing in place - ok to cover. |
| | 146 Fire Sprinklers | Needed | | | |
| | 147 Alarm Systems | Reviewed | 06/05/26 | KAHaggas | Coach Lanning's Office inspected for occupancy: sprinklers, alarms, exits all ok, ok to occupy office. |
| | 147 Alarm Systems | Needed | | | |
| | 145 Hood Suppression | Needed | | | |
| | 144 Emergency Generator | Needed | | | |
| | 153 Water/Hydrant System | Cancelled | 07/22/25 | Fire | Accidentally added duplicate inspection in error. -TRZ |
| | 153 Water/Hydrant System | Reviewed | 01/14/26 | ATBrushett | The rest of the piping to the hydrant on the southwest side of the project has been installed. Need to hydro flush and flow the system. |
| | 153 Water/Hydrant System | Cancelled | 01/13/26 | ATBrushett | |
| | 153 Water/Hydrant System | Reviewed | 01/15/26 | ATBrushett | Hydro did not hold will re test |
| | 153 Water/Hydrant System | Reviewed | 01/16/26 | KAHaggas | New fire line on south side of building from future connection to hydrant hydrostatic test ok. Hydrant set too low so will need to be changed, will retest hydrant supply from road valve to hydrant after reset at proper elevation; ok to cover. |
| | 153 Water/Hydrant System | Reviewed | 04/09/26 | ATBrushett | Flush and hydro of the underground and FDC stub outs. Still need to do the forward flow when the backflow is installed |
| | 153 Water/Hydrant System | Needed | | | |
| | 154 Standpipe | Reviewed | 04/09/26 | ATBrushett | Wrong inspection type |
| | 154 Standpipe | Needed | | | |
| | 143 Fire Regulation | Reviewed | 06/05/26 | KAHaggas | Coach Lanning's Office inspected for occupancy: sprinklers, alarms, exits all ok, ok to occupy office. |
| | 952 ERRC | Needed | | | |
| | 143 Fire Regulation | Needed | | | |
| | 150 Landscaping | Needed | | | |
| | 919 Bicycle Parking | Cancelled | 08/19/25 | Land Use | |
| | 919 Bicycle Parking | Needed | | | |
| | 157 Zoning | Needed | | | |
| | 160 Emerg Egress Light | Needed | | | |
| | 199 Final Building | Denied | 08/20/25 | LODraper | South parking lot - ADA parking access aisles required to be striped with 'NO PARKING' per the requirements in the Standards for Accessible Parking Places set forth by the Oregon Transportation Commission. OSSC Sec. 1106.8.1 |
| | 199 Final Building | Denied | 06/29/26 | LODraper | Coach's Office final inspection - ada accessibility door clearance requirement not met at entry door. This item was previously noted on the framing memo dated 4-3-26. OSSC Sections 107.4 & 1102.1 in accordance with ICC A117.1 section 404.2.3.5(C) |
| | 199 Final Building | Info Only | 07/31/26 | LODraper | Existing weight room area okay for occupancy w/trade approvals. |
| | 199 Final Building | Needed | | | |
Electrical | Active | 03/13/25 | 11/20/27 | | |
| | Inspection | Result | | Inspected | Inspector | Comment | |
| | 205 Temp Electrical | Approved | 04/02/25 | JKGoschie | EWEB at 8:34. |
| | 210 Undergrnd/Slab Elec | Reviewed | 06/27/25 | BARichardson | connector and area 2 deep |
| | 210 Undergrnd/Slab Elec | Reviewed | 07/24/25 | BARichardson | area 2 slab on grade |
| | 210 Undergrnd/Slab Elec | Reviewed | 08/04/25 | BARichardson | Main electric room deep |
| | 210 Undergrnd/Slab Elec | Reviewed | 08/22/25 | BARichardson | South IPF LV deep, connector slab on grade. |
| | 210 Undergrnd/Slab Elec | Reviewed | 09/04/25 | BARichardson | Level 1 slab on grade pour 1 is okay |
| | 210 Undergrnd/Slab Elec | Reviewed | 09/10/25 | BARichardson | Area 3 slab on grade |
| | 210 Undergrnd/Slab Elec | Reviewed | 09/17/25 | BARichardson | level 1 are2 slab on deck |
| | 210 Undergrnd/Slab Elec | Reviewed | 10/01/25 | BARichardson | level 1 connector slab and level 1 pour 4 |
| | 210 Undergrnd/Slab Elec | Reviewed | 10/22/25 | BARichardson | pour 5 level 1 slab on deck |
| | 210 Undergrnd/Slab Elec | Reviewed | 11/03/25 | BARichardson | area 4 slab on grade |
| | 210 Undergrnd/Slab Elec | Reviewed | 01/05/26 | BARichardson | Level 2M area 2c and 2d for slab on deck |
| | 210 Undergrnd/Slab Elec | Reviewed | 01/21/26 | BARichardson | NOLAR roof slab for sleeves |
| | 210 Undergrnd/Slab Elec | Reviewed | 01/26/26 | BARichardson | 2M area A slab on deck |
| | 210 Undergrnd/Slab Elec | Reviewed | 02/13/26 | BARichardson | level 1 area 4 slab on deck |
| | 210 Undergrnd/Slab Elec | Needed | | | |
| | 215 Electrical - Feeder | Cancelled | 04/30/26 | ELUnknown | |
| | 215 Electrical - Feeder | Reviewed | 07/15/26 | BARichardson | E0NHD for temp power for musco poles |
| | 215 Electrical - Feeder | Reviewed | 07/20/26 | BARichardson | See highlighted plans on site for approved one-line |
| | 215 Electrical - Feeder | Reviewed | 11/17/26 | BARichardson | feeders out of MSA in MSA distribution are ok |
| | 215 Electrical - Feeder | Reviewed | 11/18/26 | BARichardson | See highlighted plans on site for approved feeders |
| | 215 Electrical - Feeder | Needed | | | |
| | 217 Electrical Service | Reviewed | 11/17/26 | BARichardson | MSA switchgear but still need addition service location label, AIC label and GFP |
| | 217 Electrical Service | Reviewed | 11/18/26 | BARichardson | MSB switchgear but still need addition service location label, AIC label and GFP |
| | 217 Electrical Service | Cancelled | 11/24/26 | IVRUser | |
| | 217 Electrical Service | Reviewed | 11/25/26 | BARichardson | eweb. See previous comments for addition requirements prior to an approval entry |
| | 217 Electrical Service | Needed | | | |
| | 213 Bonding/Grounding | Reviewed | 06/27/25 | BARichardson | lightning ground ring for the NE corner, east side and SE corner (250cu) |
| | 213 Bonding/Grounding | Reviewed | 08/04/25 | BARichardson | rebar in the direct contact with the earth in the footing of the IPF footings along the south side this is both the grounding electrode and lightning protection with a continuous 250kcmil copper. |
| | 213 Bonding/Grounding | Info Only | 08/08/25 | BARichardson | reviewed a temp skid |
| | 213 Bonding/Grounding | Reviewed | 08/22/25 | BARichardson | 250kcmil copper continuous in 008 electrical room and tail for the ground bar in this electrical room |
| | 213 Bonding/Grounding | Reviewed | 10/01/25 | BARichardson | The metal drain bodies for the pools are bonded |
| | 213 Bonding/Grounding | Reviewed | 10/22/25 | BARichardson | The treadmill and both pool shells, perimeter and dry nich lights are okay. The tails for the rail bonding are okay |
| | 213 Bonding/Grounding | Reviewed | 11/03/25 | BARichardson | area 4 slab for 250cu grounding electrode conductor for the electric rooms and the yard |
| | 213 Bonding/Grounding | Needed | | | |
| | 225 Elec Ceiling Cover | Reviewed | 03/30/26 | BARichardson | area C connector level 0 |
| | 225 Elec Ceiling Cover | Reviewed | 04/02/26 | BARichardson | Coach offices and adjacent corridor |
| | 225 Elec Ceiling Cover | Reviewed | 04/16/26 | BARichardson | conference room on level 2 2M, intern station, level 1 corridor |
| | 225 Elec Ceiling Cover | Reviewed | 04/30/26 | BARichardson | remaining Level 0 ceilings |
| | 225 Elec Ceiling Cover | Reviewed | 05/08/26 | BARichardson | Hard lids level 1 east |
| | 225 Elec Ceiling Cover | Cancelled | 05/22/26 | JKGoschie | |
| | 225 Elec Ceiling Cover | Reviewed | 05/26/26 | BARichardson | Level 1 center Hard lids |
| | 225 Elec Ceiling Cover | Reviewed | 06/05/26 | BARichardson | locker pod |
| | 225 Elec Ceiling Cover | Reviewed | 08/24/26 | BARichardson | Level 4 hard lids for Area C and for the indoor and outdoor kitchens |
| | 225 Elec Ceiling Cover | Reviewed | 10/09/26 | BARichardson | level 1 area A and B |
| | 225 Elec Ceiling Cover | Reviewed | 10/27/26 | BARichardson | Duck nest ceiling and nutrition ceiling are okay |
| | 225 Elec Ceiling Cover | Reviewed | 11/06/26 | BARichardson | Coach's ramp wall and ceiling cover |
| | 225 Elec Ceiling Cover | Reviewed | 11/17/26 | BARichardson | level 4 pre cloud |
| | 225 Elec Ceiling Cover | Needed | | | |
| | 220 Rough Electrical | Reviewed | 01/05/26 | BARichardson | connector level 0 CMU walls |
| | 220 Rough Electrical | Reviewed | 01/21/26 | BARichardson | NOLAR CMU walls level 0 |
| | 220 Rough Electrical | Reviewed | 02/13/26 | BARichardson | cmu walls for area A sector A |
| | 220 Rough Electrical | Info Only | 02/24/26 | BARichardson | Consultation with Garrett about dedicated equipment space. |
| | 220 Rough Electrical | Reviewed | 03/30/26 | BARichardson | Area C Connector level 0 |
| | 220 Rough Electrical | Reviewed | 04/02/26 | BARichardson | Coach offices and adjacent corridor |
| | 220 Rough Electrical | Reviewed | 04/16/26 | BARichardson | conference room on level 2 2M, intern station, level 1 corridor and the new office. |
| | 220 Rough Electrical | Reviewed | 04/30/26 | BARichardson | remaining Level 0 walls and elevator at level 4 |
| | 220 Rough Electrical | Reviewed | 05/08/26 | BARichardson | walls level 1 east |
| | 220 Rough Electrical | Cancelled | 05/22/26 | JKGoschie | |
| | 220 Rough Electrical | Reviewed | 05/26/26 | BARichardson | level 1 center walls |
| | 220 Rough Electrical | Reviewed | 06/05/26 | BARichardson | locker pod and level 1 north weight room walls |
| | 220 Rough Electrical | Reviewed | 07/15/26 | BARichardson | Level1 area A walls |
| | 220 Rough Electrical | Reviewed | 07/20/26 | BARichardson | Hard lids for 1A |
| | 220 Rough Electrical | Reviewed | 07/22/26 | BARichardson | Northside walls for level 4 area C excluding outdoor kitchen |
| | 220 Rough Electrical | Reviewed | 10/09/26 | BARichardson | South area B level 1, |
| | 220 Rough Electrical | Reviewed | 11/06/26 | BARichardson | Coach's ramp wall and ceiling cover |
| | 220 Rough Electrical | Needed | | | |
| | 230 Limited Energy | Needed | | | |
| | 299 Final Electrical | Reviewed | 06/05/26 | BARichardson | coaches office. |
| | 299 Final Electrical | Reviewed | 07/31/26 | BARichardson | Lobby L101, Office 104, Intern Station 215, Timing Track wiremold in existing weight room. |
| | 299 Final Electrical | Needed | | | |
| | 265 Arc Reduction 1200A or more | Needed | | | |
| | 270 GFP 1000A or more at 480V | Needed | | | |
Fire | Active | 01/17/25 | 11/20/27 | | |
| | Inspection | Result | | Inspected | Inspector | Comment | |
| | 840 Water/Hydrant System | Reviewed | 07/24/25 | ATBrushett | Piping inspection has been competed up to the footing of the new building on the east side of the project. The install is in accordance with the original civil drawings, however the contractors still needs to provide the differed submittal for the underground fire line. Hydro was completed but the new hydrant line needs to be flushed. |
| | 840 Water/Hydrant System | Reviewed | 10/24/25 | GRGordon | Underground Fire Line Open Cover Inspection. Permit number: 24-07375-01.
Open cover inspection of approximately 300 feet of 8-inch AWWA C-900, UL listed, CPVC pipe; two 45 degree ells; two 11 1/4 degree ells; mega lugged; joint restraints in place.
Will continue run to the west to the fire hydrant at a later date. Will connect to the building at a later date.
OK to Cover |
| | 840 Water/Hydrant System | Reviewed | 01/12/26 | ATBrushett | Piping for the 4 field level standpipes has been inspected and is ok to cover. Hydro on the piping for the standpipes OK. Wil need to flush the standpipe system once the system gets water. |
| | 849 Final Fire | Reviewed | 06/05/26 | KAHaggas | Coach Lanning's Office inspected for occupancy: sprinklers, alarms, exits all ok, ok to occupy office. |
| | 849 Final Fire | Needed | | | |
Mechanical | Active | 10/27/25 | 11/20/27 | | |
| | Inspection | Result | | Inspected | Inspector | Comment | |
| | 410 Underfloor Mechanical | Needed | | | |
| | 416 Rough Gas Piping | Reviewed | 12/12/25 | LODraper | L0 main gas piping from meter to water heater room on test holding at 100 psi. This piping is intended to be used for temporary purposes and has been green tagged. Full approval is contingent on verification that the gas piping plans have been reviewed and approved by the COE and field approval of the remainder of the gas piping for the remaining portions of the project. OMSC Sec. 106.1 |
| | 416 Rough Gas Piping | Denied | 01/05/26 | LODraper | Additional gas piping at connector serving L0-L4 not holding test pressure OMSC Sec. C406.4.1 |
| | 416 Rough Gas Piping | Reviewed | 01/07/26 | LODraper | Connector bldg main gas piping up to L4 kitchen (for temp heat) on test holding at 100psi. Pressure test approved for 2# psig |
| | 416 Rough Gas Piping | Reviewed | 05/22/26 | LODraper | L1-L4 gas piping serving L4 connector appliances on test holding at 60 psi |
| | 416 Rough Gas Piping | Needed | | | |
| | 450 Final Gas Piping | Needed | | | |
| | 420 Rough Mechanical | Info Only | 01/13/26 | LODraper | Preliminary review of connector building roof curb anchorage requirements. Drawings for the anchorage of the mechanical units at this location have not been submitted and approved by the City yet. OSSC Sec. 107.4, OMSC Sec. 106.4.1 |
| | 420 Rough Mechanical | Reviewed | 01/20/26 | LODraper | L0 sector C MDF room refrigerant piping on test holding at 500+ psi |
| | 420 Rough Mechanical | Reviewed | 01/23/26 | LODraper | L0 connector and HDC hydronic and condensate piping on test holding at 100 psi. No approval for supports yet as deferred submittal for suspended MEPF seismic anchorage has not been submitted to the city. OSSC Sec. 107.4 |
| | 420 Rough Mechanical | Reviewed | 01/30/26 | LODraper | Level 0 sector C south ice room cooling unit DFCU 0C-03 and 2M weight room unit FCU 2B-13 hydronic and condensate piping on test holding at 100 psi |
| | 420 Rough Mechanical | Denied | 02/11/26 | LODraper | L0 sector C dryer venting in progress. Need to provide additional routing details related to supporting requirements that are not noted on the plans. OMSC Sec. 106.4.1 |
| | 420 Rough Mechanical | Reviewed | 02/18/26 | LODraper | NOLR level 1 sector B hydronic floor piping on test at GL 1.6-4.5 - holding at 75-80 psi |
| | 420 Rough Mechanical | Reviewed | 02/19/26 | LODraper | NOLR level 1 additional hydronic piping at sector A on test holding at 80 psi |
| | 420 Rough Mechanical | Reviewed | 02/23/26 | LODraper | NOLR level 1 remaining radiant floor hydronic piping on test observed starting at 80 psi, dropped to 78 psi over the course of 30 minutes. Contractor to check for potential leaks and recall if found |
| | 420 Rough Mechanical | Reviewed | 02/24/26 | LODraper | NOLR level 1 remaining radiant floor hydronic piping on test holding at 80 psi. |
| | 420 Rough Mechanical | Reviewed | 02/26/26 | LODraper | NOLR roof level curb attachments observed - drawings not submitted to the COE. OSSC Sec. 107.4 |
| | 420 Rough Mechanical | Reviewed | 03/10/26 | LODraper | L0 sector C dryer duct fire wrap installed per MII |
| | 420 Rough Mechanical | Reviewed | 03/13/26 | LODraper | L4 existing coach's office heating and chilled water piping on test holding at 80 psi |
| | 420 Rough Mechanical | Denied | 03/20/26 | LODraper | Seismic anchorage of suspended MEPF equipment. This submittal has not been submitted to the City of Eugene for review. It will not be inspected until it has been submitted to the COE. OSSC Sec. 107.3.4.1 |
| | 420 Rough Mechanical | Reviewed | 03/25/26 | LODraper | L1 east barbershop hot water piping on test holding at 80 psi |
| | 420 Rough Mechanical | Cancelled | 03/26/26 | LODraper | Not ready. OSSC Sec. 110.5 |
| | 420 Rough Mechanical | Cancelled | 03/29/26 | LODraper | Not ready. OSSC Sec. 110.5 |
| | 420 Rough Mechanical | Reviewed | 03/31/26 | LODraper | NOLR level 1 sector B hydronic piping testing approved from GL 1-5.5 south to line E |
| | 420 Rough Mechanical | Reviewed | 04/02/26 | LODraper | L4 coach's office above ceiling except bathroom and marshal's office |
| | 420 Rough Mechanical | Reviewed | 04/06/26 | LODraper | Chilled water piping 2M mech room to office 104 on test holding at 60 psi |
| | 420 Rough Mechanical | Reviewed | 04/07/26 | LODraper | L0 connector toilet rooms ok |
| | 420 Rough Mechanical | Reviewed | 04/14/26 | LODraper | NOLR level 1 mechanical piping seismic restraints |
| | 420 Rough Mechanical | Reviewed | 04/17/26 | LODraper | Connector L4-roof refrigerant piping on test holding at 550 psi, HDC office 104 above grid ducting, L2M conference room above grid ducting and FC unit seismic |
| | 420 Rough Mechanical | Reviewed | 04/22/26 | LODraper | L0 lobby and L2M intern stations above lid ducting ok |
| | 420 Rough Mechanical | Cancelled | 05/01/26 | IVRUser | |
| | 420 Rough Mechanical | Reviewed | 05/04/26 | LODraper | Chilled water piping from L0 chiller room up to 2M and refrigerant piping for HP-0B-01 on test, drying room ducting ok for cover |
| | 420 Rough Mechanical | Reviewed | 05/08/26 | LODraper | L0 chiller room condenser water piping on test holding at 150 psi, L1 sector B bathroom and locker room east of line 2.5 above ceiling ok |
| | 420 Rough Mechanical | Reviewed | 05/12/26 | LODraper | L0-L4 south connector shafts. Dryer duct installation specifications still outstanding. OMSC Sec. R106.4.1 |
| | 420 Rough Mechanical | Reviewed | 05/13/26 | LODraper | L1 connector mechanical piping, L0-L4 condensate piping - all on test holding 100 psi |
| | 420 Rough Mechanical | Reviewed | 05/15/26 | LODraper | NOLR classroom above ceiling ducting seismic restraints verified |
| | 420 Rough Mechanical | Reviewed | 05/18/26 | LODraper | North connector L1-roof hydronic piping on test holding at 100 psi |
| | 420 Rough Mechanical | Reviewed | 05/22/26 | LODraper | L2M sector C mechanical piping seismic restraints ok |
| | 420 Rough Mechanical | Reviewed | 05/26/26 | LODraper | NOLR level 1 west locker room above ceiling ok |
| | 420 Rough Mechanical | Reviewed | 05/29/26 | LODraper | The rest of 1B north Chilled Weld Pipe- through floor- Pool room piping and through the coil kits of the 3 Electrical room cooling units. Welded heating water pipe from level 0 hallway isolation valves- pool room piping- existing pipe already tested- both coils and kits of Drying room units and piping/coil and kit of Chiller Room Unit Chilled Water in Chiller room from isolation valve to chiller room unit and electrical room unit south of chiller room - all on test holding 100+ psi |
| | 420 Rough Mechanical | Reviewed | 06/08/26 | LODraper | South connector shaft ducting fire wrap levels 1-4. NOLR level 1 sector B shower area SA/EA ducts |
| | 420 Rough Mechanical | Reviewed | 06/10/26 | LODraper | Connector level 4 grease duct light test approved |
| | 420 Rough Mechanical | Reviewed | 06/22/26 | RZSteiner | hydronic pressure test level 0-1 sector A and condensate level 1 |