City of Eugene
Planning & Development
Building and Permit Services
Permit Number: 24-07286-01
Date: 7/20/2025
Address: 2270 OAKMONT WAY
Project Description: Electrical for new Tesla Charging Station.
Application Type:
Commercial
Status:
Issued
Scope of Work:
Specialty Permit
Zoning:
Community Commercial District
Map:
17-03-29-10
Tax Lot:
00403
Subdivision:
Addition:
Lot:
Block:
Date Received:
10/03/24
# Bedrooms:
0
Commitment Date:
10/14/24
# Dwelling Units:
0
Ready to issue as of:
10/14/24
In Flood Plain:
Project Coordinator:
Chris Strang
Phone:
541-682-8115
  
Sign Standards:
 
CONTRACTOR DATA
Type
Contractor
Electric
INNOVATIVE ELECTRICAL SOLUTIONS LLC
PLAN REVIEW SUMMARY
Plan review data displayed is the most current for each review. The applicant will receive notification of all issues needing additional information after all reviews on a project have been completed. Supplemental Information (SI) can be submitted prior to or after permit issuance. If you have any questions regarding your project, contact CMStrang at 541-682-8115 or send email to Christopher.M.Strang@ci.eugene.or.us. Also note that some reviews (i.e., fire alarms, fire sprinklers) are deferred submittals and will be reviewed after original permit(s) have been issued.
Status Definitions
Pending
=
Review has not been started
Review
=
Under review
Waiting
=
Review for individual review has been completed, waiting for a response
External Wait
=
All reviews for project have been completed, waiting for a response
Approved
=
Review has been approved
Information
=
Information only, review not approved
Denied
=
Project cannot be approved as submitted
For information regarding the review of your project or the commitment date for completion of review, please contact your project coordinator, CMStrang, at Christopher.M.Strang@ci.eugene.or.us or by phone at 541-682-8115.
Plan Review
Status
Review Completion Date
Project Coordination, Application Submittal
Approved
10/14/24
Building, Application Submittal
Information
10/04/24
Electrical, Application Submittal
Approved
10/11/24
PERMITS AND INSPECTIONS
Permit Type
Status
 
Issued Date
Expiration Date
Completion Date
 
Electrical
Finished
10/14/24
07/21/25
01/22/25
 
 
Inspection
Result
 
Inspected
Inspector
Comment
 
 
210 Undergrnd/Slab Elec
Approved
10/29/24
BARichardson
 
 
215 Electrical - Feeder
Approved
01/22/25
BARichardson
 
 
217 Electrical Service
Approved
01/22/25
BARichardson
 
 
220 Rough Electrical
Not Needed
12/10/24
BARichardson
 
 
299 Final Electrical
Approved
01/22/25
BARichardson
 
 
265 Arc Reduction 1200A or more
Approved
12/10/24
BARichardson
 
 
270 GFP 1000A or more at 480V
Approved
12/10/24
BARichardson
 
To request an inspection go to https://pdd.eugene-or.gov/BuildingPermits/InspectionLogin.
For more information call 541-682-5283.
FEES
Fees
Total Due
Amount Paid
Paid Date
Amount Due
Electrical
$1,276.23
$1,276.23
 
$0.00
Electric Plan Check
$274.10
$274.10
10/14/24
$0.00
Over 1000 amps or volts
$753.00
$753.00
10/14/24
$0.00
Branch Circuits w/ Feeder or Service
$30.15
$30.15
10/14/24
$0.00
State Surcharge, Electrical
$102.69
$102.69
10/14/24
$0.00
Electric Technology Admin Fee, Local
$21.14
$21.14
10/14/24
$0.00
Electric Plan Check Admin
$24.67
$24.67
10/14/24
$0.00
Electric Admin Fee, State
$70.48
$70.48
10/14/24
$0.00
Total All Fees
$1,276.23
$1,276.23
 
$0.00
Page 1 of 1
Date: 7/20/2025